What is the purpose of the WBS?

A.

To show which work elements have been assigned to organizational units.

B.

To ensure that all work within a project is identified and defined within a common framework.

C.

To show the organizational structure of a program.

D.

all of the above

A project plan is:

A.

A formal, approved document used to guide both project execution and project control.

B.

A document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.

C.

A narrative description of products or services to be supplie

D.

A document describing the organizational breakdown structure of the company.

Who should contribute to the development of a project plan?

A.

Project manager

B.

Entire project team including project manager

C.

Senior management

D.

Just the planning department

With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is _____.

A.

30.0

B.

22.5

C.

25.0

D.

27.5

Which of the following is an output of a Verify Scope process?

A.

Formal acceptance

B.

WBStemplate

C.

SOW acceptance

D.

Rework

The unique identifiers assigned to each item of a WBS are often collectively known as:

A.

The work package codes

B.

The project identifiers

C.

The code of accounts

D.

The element accounts

Key Management skills include:

A.

Leading

B.

Communicating

C.

Negotiating

D.

All of the above

Which ensures that project objectives are met by monitoring and measuring progress and taking corrective action when necessary.

A.

Project controls

B.

Controlling process

C.

Control logs

D.

Project chart

A Project Cost Management plan is created as a part of:

Develop Project Management Plan process

Control Costs process

Determine Budget process

Estimate Costs process

Which is generally the least accurate.

A.

Using stakeholders to predict cost

B.

Parametric modelling

C.

Analogous estimating

D.

Computerized estimating

Which of the following is ensuring that all features and functions are included in a product or service

A.

Project scope

B.

Project verification

C.

Project control

D.

Product scope

Which of the following models of conflict resolution allows a cooling off period, but seldom resolves the issue in the long term?

A.

Problem solving

B.

Withdrawal

C.

Forcing

D.

Smoothing

Staffing requirements do not define:

A.

What types of skills are required

B.

What time frames

C.

What kinds of individuals or groups

D.

What type of resource planning is required

Which is the most important element of a Project Management Plan that is useful in the Develop Human Resource Plan process:

A.

Risk Management activities

B.

Activity Resource requirements

C.

Budget Control activities

D.

Quality Assurance activities

Which of the following is not true for a Resource Leveling:

A.

Project's Critical path may be altered

B.

Reverse resource allocation scheduling

C.

Resource based scheduling method

D.

None