The following is a network diagram for a project.

The free float for Activity H is how many days?

A.

4

B.

5

C.

10

D.

11

Requirements documentation will typically contain at least:

A.

Stakeholder requirements, staffing requirements, and transition requirements.

B.

Business requirements, the stakeholder register, and functional requirements.

C.

Stakeholder impact, budget requirements, and communications requirements.

D.

Business objectives, stakeholder impact, and functional requirements.

The following is a network diagram for a project.

How many possible paths are identified for this project?

A.

3

B.

4

C.

6

D.

7

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

A.

Identify Risks

B.

Control Risks

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

The specific technique for identifying a problem, discovering the causes that lead to it, and developing preventive actions is:

A.

Inspection

B.

Use of quality checklists

C.

Root cause analysis

D.

Use of matrix diagrams

Which tool or technique is required in order to determine the project budget?

A.

Cost of quality

B.

Historical relationships

C.

Project management software

D.

Forecasting

The following is a network diagram for a project.

The free float for Activity E is how many days?

A.

2

B.

3

C.

5

D.

8

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

16

Activity cost estimates are quantitative assessments of the probable costs required to:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

The following is a network diagram for a project.

What is the critical path for the project?

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Stakeholder communication requirements should be included as a component of:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Which of the following is a tool and technique for Estimate Activity Durations?

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

What is an objective of the Develop Project Team process?

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Closing

A required input for Create WBS is a project:

A.

quality plan.

B.

schedule network.

C.

management document update.

D.

scope statement.

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

A.

Projectized

B.

Weak matrix

C.

Functional

D.

Balanced matrix

Which of the following tools or techniques is used for Estimate Activity Durations?

A.

Critical path method

B.

Rolling wave planning

C.

Precedence diagramming method

D.

Parametric estimating