What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:
Typical outcomes of a project include:
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
In a project, total float measures the:
Change requests are processed for review and disposition according to which process?
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
An input to the Identify Stakeholders process is:
An output of the Direct and Manage Project Work process is:
Which tool or technique is used in the Estimate Costs process?
A key benefit of the Manage Communications process is that it enables:
The Perform Integrated Change Control process occurs in which Process Group?
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
Which item is an example of personnel assessment?
Lessons learned are created and project resources are released in which Process Group?
Inputs to the Plan Schedule Management process include:
Which tool or technique is an examination of industry and specific vendor capabilities?
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
An input to the Manage Project Team process is:
A large portion of a projects budget is typically expended on the processes in which Process Group?
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
An output of the Create WBS process is:
The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:
During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
An output of the Plan Quality Management process is:
Once the make-or-buy analysis is completed, which document defines the project delivery method?
A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?
A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?
A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?
When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?
What process is included in Project Schedule Management?
Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?
Which role does the project manager resemble best?
Responsible, accountable, consult and inform (RACI) is an example of which of the following?
During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project's components. What should be included in the WBS?
What is the difference between verified and accepted deliverables?
During which process of Project Cost Management does a project manager produce the cost baseline?
Which set of activities should a project manager use as part of the Develop Team process?
Which of the following is used as an input to prepare a cost management plan?
At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?
A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?
A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?
Which statement about identification and engagement of stakeholders during a project is correct?
Which of the following documents ate created as part of Project Integration Management?
Which of the following are outputs of the Define Scope process in Project Scope Management?