Who is responsible for initiating a project?
During project selection, which factor is most important?
Which of the following is an output of Close Procurements?
Which is one of the determining factors used to calculate CPI?
Which activity may occur at project or phase closure?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
Match the influence with its corresponding category of influence.
Perform Quantitative Risk Analysis focuses on:
Directing another person to get from one point to another using a known set of expected behaviors and the ability to lead a team and inspire them to do their jobs well is related to?
A project manager Is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement. Which process does this typically represent?
Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take into account for risk management in this environment?
What is one of the main purposes of the project charter?
With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?
How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?
Howls program success measured?
A project manager is searching for solutions that bring some degree of satisfaction to all parties in order to temporarily resolve a conflict. What conflict management technique is described in this situation?
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages.
Which technique is the project manager using?
In an agile and adaptive project, which scope management entity invokes stakeholder engagement?
The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.
What are these elements called?
Which of the following is an example of facit knowledge?
The Agile principle "welcome changing requirement, even late in development" relates to which agile manifesto?
What is the first step in the Stakeholder Management process?
When should Project Risk Management be conducted?
What is a tailoring consideration in Project Integration Management?
What organizational asset can influence the Plan Risk Management process?
What are the key tools for managing project knowledge?
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?
At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?
Why is tailoring required in a project?
Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?
What should a project manager use to determine how much money is needed to complete a project?
It you established a contingency reserve including time, money, and resources, how are you handling risk?
A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
Which of the following sets are inputs to the Collect Requirements process?
Which of the following tasks focuses on decomposing work packages?
What are the objectives of Initiation processes?
Which of the following documents ate created as part of Project Integration Management?
Match the project manager's sphere of influence with the associated primary role.
Which of the following are outputs from the process of creating a work breakdown structure (WBS)?
What is the role of project management in terms of organizational strategy?
A project manager is identifying the risks of a project. Which technique should the project manager use?
What important leadership quality/qualities should project managers possess?
In which of the Risk Management processes is the project charter used as an input?
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?
In which organizational structure would the project manager have most authority?