Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Which characteristic do projects and operational work share in common?

A.

Performed by systems

B.

Constrained by limited resources

C.

Repetitiveness

D.

Uniqueness

In an agile and adaptive project, which scope management entity invokes stakeholder engagement?

A.

Collect Requirements

B.

Create work breakdown structure (WBS)

C.

Plan Scope Management

D.

Scope Baseline

Which sentence summarizes the salience model?

A.

Classifies stakeholders based on assessment of their power, urgency and legitimacy

B.

A chart in which the Stakeholders are ropiosented as dots according to then level ol power and influence

C.

A three-dimensional model that ran be useful to engage the stakeholder community

D.

Classifies stakeholders and the project toam by the impact of their work in the project

Which of the following correctly explains the term " progressive elaboration ' ?

A.

Changing project specifications continuously

B.

Elaborate tracking of the project progress

C.

Elaborate tracking of the project specifications with a change control system

D.

Project specifications becoming more explicit and detailed as the project progresses

What document gathers all of the lessons learned at the end of a phase or project

A.

Lessons learned register

B.

Lessons learned list

C.

Lessons learned project asset

D.

Lessons learned repository

In the project charter process, which three of the following are discussed during meetings held with stakeholders? (Choose three) D Cost

A.

High-level deliverables

B.

Success criteria

C.

Project objectives

D.

Phase transitions

What is a tailoring consideration in Project Integration Management?

A.

Validation and control

B.

Benefits

C.

Technology support

D.

Physical location

Which organizational process asset can make an impact on the outcome of a project?

A.

Political climate

B.

Leadership style

C.

Financial data repository

D.

Organizational structure types

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

A.

Supportive

B.

Leading

C.

Neutral

D.

Resistant

An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.

Which of the following changes has caused this loss in productivity?

A.

Two of the team members have been working in silos using different methods to validate their performance.

B.

The team velocity was measured in the third sprint since the tool to measure velocity was introduced only in the third sprint.

C.

The team picked up technical debt items in the third sprint as technical debt can only be picked up after completing two sprints.

D.

Two of the team members were asked to do multitasking, which they did not do in the previous two sprints.

An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?

A.

Product and sprint backlog

B.

Key performance indicators (KPIs) and baseline

C.

Increments and bottlenecks

D.

Burndown and burnup charts

Which of the following is a tool and technique for Estimate Activity Durations?

A.

Parametric estimating

B.

Monte Carlo analysis

C.

Alternatives analysis

D.

Bottom-up estimating

An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.

Which two of the following items should be included in the planning? (Choose two)

A.

Daily scrum

B.

Sprint backlog

C.

Sprint review

D.

Increments

E.

Sprint retrospective

What can increase the complexity of the Manage Stakeholder Engagement process?

A.

The project must be of high quality.

B.

The stakeholders are from different countries.

C.

The project must comply with strict local government regulations.

D.

The project has a tight budget and timeline.

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

A.

Work packages.

B.

Accepted deliverables.

C.

The WBS dictionary.

D.

The scope baseline.

A project team is reviewing project performance. During the execution phase, the project team discovers that there is an off-the-shelf (OTS) product, which could reduce the timeline for development.

What should the project manager do next?

A.

Update the project management plan.

B.

Add the discovery to the assumptions.

C.

Evaluate the risk with the project team.

D.

Conduct an opportunity analysis with the team.

A project manager should communicate to stakeholders about resolved project issues by updating the:

A.

project records

B.

project reports

C.

stakeholder notifications

D.

stakeholder register

Which set of tools and techniques is useful for estimating activity durations for the project schedule?

A.

Brainstorming, Monte Carlo simulation, analogous estimation

B.

Three-point estimation, resources leveling, iteration burndown chart

C.

Milestone charts, parametric estimation, schedule baseline

D.

Parametric estimation, three-point estimation, meetings

A project manager needs to determine the schedule variance (SV). The project manager ' s latest schedule indicates 14 units of work completed against a plan of 23 units.

What is the SV?

A.

-9

B.

37

C.

9

D.

322

Which of the following is a tool or technique of the Define Activities process?

A.

Rolling wave planning

B.

Precedence diagramming method (PDM)

C.

Alternatives analysis

D.

Parametric estimating

What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?

A.

Tornado diagrams and influence diagrams

B.

Detectability bubble charts and probability and impact matrix

C.

Hierarchical charts and burndown charts

D.

Flow charts and responsible, accountable, consult, and inform (RACI) charts

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

A.

Informal communication

B.

Internal communication

C.

Formal communication

D.

Horizontal communication

A project manager is creating a project charter to provide a direct link between the project and the organization ' s strategic objectives. What must be considered when creating this document?

A.

High-level requirements and the project team

B.

Key stakeholder list and contingency reserve

C.

Detailed milestone schedule and project objectives

D.

Project purpose and high-level project description

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

The project manager is working in the Resource Management process. Which items may the project manager need to include in the team charter?

A.

Cultural norms, roles and responsibilities, and organizational chart

B.

Assumption logs, resource calendars and training schedule

C.

Communication guidelines, conflict resolution process, and team agreements

D.

Company policies, recognition plan, and roles and responsibilities

In which Process Group are lessons learned documented?

A.

Planning

B.

Closing

C.

Executing

D.

Initiating

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Closes Project or Phase

D.

Perform itegrated Change Control

A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?

A.

Detailed estimation

B.

Lightweight estimation

C.

Parametric estimation

D.

A mix of them

Which tool or technique is used in the Perform Integrated Change Control process?

A.

Decomposition

B.

Modeling techniques

C.

Resource optimization

D.

Meetings

One of the objectives of a quality audit is to:

A.

highlight the need for root cause analysis.

B.

share the process documentation among stakeholders.

C.

offer assistance with non-value-added activities.

D.

identify all of the gaps or shortcomings.

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

A.

Start-to-start (SS).

B.

Start-to-finish (SF).

C.

Finish-to-start (FS).

D.

Finish-to-finish (FF).

During the execution of a predicted project, the need for a new product feature has been proposed by the customer. What should the project manager do next?

A.

Decline any request by the customer and continue the project as initially planned.

B.

Accept the customer ' s request and continue with elicitation of the new product features.

C.

Investigate the possibility of using the management reserve to pay for the extra hours the team will need to work.

D.

Investigate the effect that such an integration will have on the project plan and propose a change request.

Which characteristic defines the Delphi technique of group decision-making?

A.

The participants must use their expertise to determine the best option.

B.

The decision is based on eliminating the options that are too expensive.

C.

The decision is based on a predefined algorithm and the highest score.

D.

The participants must create a list of options, rank them, and then vote.

When does the project team determine which dependencies are discretionary?

A.

Before the Define Activities process

B.

During the Define Activities process

C.

Before the Sequence Activities process

D.

During the Sequence Activities process

A project is at the closing stage. The project manager asks the team to perform closing functions at the next meeting. Which two procedures will the project team perform? (Choose two)

A.

Project audit

B.

Deliverable acceptance

C.

Risk register tracking

D.

Stakeholder mapping

E.

Issue log update

What describes the relationship between projects, programs, and portfolios?

A.

Portfolio management focuses on doing the " right " programs and projects.

B.

Project management focuses on doing the " right " programs and portfolios.

C.

Program management focuses on doing the " specific " portfolios and projects.

D.

Portfolio management focuses on doing the ' ' specific’’ programs and projects.

Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

A.

Bottom-up

B.

Three-point

C.

Parametric

D.

Analogous

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

A.

Monitor and Control Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

An example of a group decision-ma king technique is:

A.

Nominal group technique.

B.

Majority.

C.

Affinity diagram.

D.

Multi-criteria decision analysis.

Which of the following is an output of the Define Activities process?

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?

A.

Move these user stories back to the product backlog for reprioritization.

B.

Remove these user stories as they are not important.

C.

Advance these user stories to the top of the next sprint backlog.

D.

Complete these user stories in the current sprint and extend the sprint length.

Which tool is used to develop technical details within the project management plan?

A.

Expert judgment

B.

Project management methodology

C.

Project management information system (PMIS)

D.

Project selection methods

Which Process Group ' s purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

The process of identifying and documenting relationships among the project activities is known as:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Which element does a project charter contain?

A.

Management reserves

B.

Work breakdown structure

C.

Stakeholder list

D.

Stakeholder register

During the execution of a project, a stakeholder asks a project manager whether the project is falling behind or ahead of its baseline schedule. The project manager calculates the earned value analysis (EVA) schedule variance and it comes out to be zero. Which of the following is correct about the EVA schedule variance?

A.

It is calculated incorrectly, as it cannot be zero for an in-flight project; otherwise the project is completed.

B.

Change it to a negative value to show that the project is falling behind.

C.

Zero is a perfectly valid value for an in-flight project; hence share the zero value with the stakeholder.

D.

Change it to a positive value to show that the project is ahead of its baseline schedule.

Which activity may occur at project or phase closure?

A.

Acceptance of deliverables

B.

Change requests

C.

Project management plan updates

D.

Benchmarking