A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
High-level project risks are included in which document?
Those who enter into a contractual agreement to provide services necessary for a project are:
Stakeholder communication requirements should be included as a component of:
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
Every project creates a unique product, service, or result that may be:
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
The process of defining how the project scope will be validated and controlled is known as:
Perform Integrated Change Control is the process of:
An output of the Perform Integrated Change Control process is:
Which items are components of a project management plan?
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
Which is an enterprise environmental factor?
Project Scope Management is primarily concerned with:
Whose approval may be required for change requests after change control board (CCB) approval?
Analytical techniques are a tool and technique of which process in Project Procurement Management?
The following is a network diagram for a project.
What is the critical path for the project?
For a stakeholder with low interest and high power, the project manager should:
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
Specification of both the deliverables and the processes is the focus of:
Which tool or technique is required in order to determine the project budget?
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
The following is a network diagram for a project.
The shortest non-critical path for the project is how many days in duration?
Which element does a project charter contain?
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost variance (CV) for Task 6?
A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
Organizational theory is a tool used in which Project Human Resource Management process?
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?
Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
An input used in developing the communications management plan is:
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
The Perform Quality Assurance process occurs in which Process Group?
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?
An element of the project scope statement is:
A key benefit of the Manage Communications process is that it enables:
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
Which tools or techniques are used in the Plan Schedule Management process?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
Which tool or technique is effective in a project in which the deliverable is not a service or result?
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
An input to Close Project or Phase is:
An output of the Validate Scope process is:
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
Reserve analysis is a tool and technique used in which process?