The project manager and project team are developing approximations of the cost of resources needed to complete the project work. On which process are they working?
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?
During the execution phase of a multibillion-dollar project, the project manager encountered performance issues with some of the team members. In a performance review meeting, the project manager noticed that the team members do not follow SMART objectives.
What are SMART objectives?
What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?
Which of the following projects is a quality candidate for adaptive approaches?
A project team is working on relocating offices to another building and providing new furniture. The new furniture was purchased from an international vendor. The price was negotiated in a foreign currency, and due to changes in the exchange rate, the cost has increased by 10%. There is no contingency in the project budget. What should the project manager do?
For a 10-day project, activity B ' s duration is three days, and activity C’s duration is two days What is the duration of activity A if activities B and C are performed in parallel?
What internal enterprise environmental factor (EEF) can impact a project?
A project team for a marketing company is acquiring leaflets and materials from competitors. The team is working on a project to release new products, and they are trying to get ideas on how to most efficiently market these new products.
Which activity is the project team conducting?
A project manager is performing a specific process and has..........is being referred to?
A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?
A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager. What should the project manager do to address this issue?
A business analyst has encountered a conflict related to competing requirements on an existing project. What tool should the business analyst use to resolve this issue?
What three strategies are used to respond to threats?
What is an example of an emerging trend in procurement management?
A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented if for decision. What was project manager trying to do?
A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month each. This will help this small enterprise to have a return on investment (ROI) as the project runs from the first cycle. Which methodology should the project manager adopt and implement in the project?
While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.
What should the team do to ensure that this situation is managed?
A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.
Which of the following project delivery approaches should be recommended?
In addition to the project charter, what other artifact is produced as a result of the Develop Project Charter process'?
Match the life cycle type to when its requirements are defined.

A team has been tasked with designing a product to address a problem they have never faced before. The project team is struggling to get traction as the solutions are not clear. What should the project manager do next?
What risk response strategy involves removing high- risk scope elements from a project?
Which three of the following interpersonal skills does a project manager rely on when developing the project management plan? (Choose three)
A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?
A business analyst sent multiple meeting requests via instant message to a subject matter expert (SME) working in another country but did not receive a response. What should the business analyst do to reduce the likelihood of this occurring in the future with other stakeholders distributed across multiple locations?
A company has implemented an adaptive project management framework for a new project. When planning for an iteration, how should risks be addressed? Choose two.
A project manager is responsible for delivering new software for their company. Based on previous experiences, the project manager decides to use the dynamic systems development method (DSDM). The project manager will use this method to prioritize the scope to meet project constraints.
Which elements are included in the DSDM framework?
What tool or technique is primarily used to plan risk responses'?
A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.
What should the project manager do to address this issue?
What does earned value (EV) measure?
Which method should be used to elicit a cross-functional requirement?
A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members knows their roles and responsibilities.
What are the four elements of a RACI chart?
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?
A construction project is underway, and during... tasks impacted the painting work
A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job What kind ot relationship between the tasks impacted the painting work?
A Project manager is using agile in a project. As development life cycle is adaptive, how does the project manager handle key stakeholder involvement?
An adaptive project manager is told that a new industry regulation will affect an upcoming deliverable. Where should this be recorded?
A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity's prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.
How should the project manager proceed?
What specific quality considerations should be examined while completing Quality Management plan?
A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?
A project manager is working on the communications management plan. Which of these documents are inputs to consider?
A project team is starting to work on a project based on a Kanban approach. In order to frame the capacity of the team's workflow at any moment, the project manager will need to restrict the maximum amount of activities to be performed.
Which element will the project manager handle?
The project manager is new to the company in order to effectively manage the project, which components of the organizational governance framework does the project manager need to take into account?
How can a project manager ensure effective project stakeholder engagement?
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?
Which output is the approved version of the time-phased project budget?
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
An output of the Perform Integrated Change Control process is:
Project management processes ensure the:

A screenshot of a login box Description automatically generated