Which item is an example of personnel assessment?
An output of the Develop Project Team process is:
Which cost is associated with nonconformance?
Which tool or technique is used to manage change requests and the resulting decisions?
The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
Which process determines the risks that may affect the project and documents their characteristics?
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Which tool or technique is an examination of industry and specific vendor capabilities?
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
Which input to the Plan Risk Management process provides information on high-level risks?
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
An output of the Direct and Manage Project Work process is:
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
An input to the Identify Stakeholders process is:
Which tool or technique is used in validating the scope of a project?
Which tool or technique is used in the Perform Integrated Change Control process?
Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
The process of identifying and documenting relationships among the project activities is known as:
An input to the Plan Stakeholder Management process is:
Which tool or technique is used in the Estimate Costs process?
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
Stakeholder satisfaction should be managed as a key project:
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
An input to Develop Project Charter is a/an:
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Which document defines how a project is executed, monitored and controlled, and closed?
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
Inputs to the Plan Schedule Management process include:
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
Match each Project Cost Management process with its appropriate keyword
A project manager is reviewing a few techniques that can be used to evaluate solution results. The intent is to uncover whether the solution responds properly to unintended cases.
Which evaluation technique should be used here?
During the requirements verification process, stakeholders are finding many errors in the requirements definition. What could the business analyst have done to avoid these errors?
Which three processes are generally included in risk management? (Choose three)
The project manager has following information about duration for an activity:
* Most likely [tM] - 15 days
* Pessimistic [tP] - 20 days
* Optimistic [tO] - 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
A project manager is leading a technology project that is about to enter the execution phase. The project requires the procurement of certain key components from an external vendor. The project manager has been notified that because of a government regulation, some parts can no longer be used in the country and the vendor will be unable to deliver them.
What should the project manager do?
A product owner wants to ensure that the project's requirements, including product requirements, are met and validated. To do this project manager wants.
Match each process to its definition.
Which component of the project management plan should be updated if a change occurs?
A new project was approved and the project manager is discussing the most suitable delivery approach with the project sponsor. Which three of the following are characteristics of a traditional project delivered using a linear delivery approach? (Choose three)
A project team is meeting to seek solutions on a new problem that occurred recently. The meeting is comprised of two parts: the first is a generation of ideas and the second is an analysis.
Which technique is the team using?
What purpose does the hierarchical focus of stakeholder communications serve?
Match the method for categorizing stakeholders with its corresponding description
In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?
Which document can help a project manager to leverage historical project information?
A few black text boxes Description automatically generated with medium confidence
A group of words on a white background Description automatically generated
A screenshot of a computer Description automatically generated