Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

What is the best tool to calculate the critical path on a project?

A.

Critical chain method

B.

Graphical evaluation and review technique (GERT) diagram

C.

Gantt chart

D.

Project network diagram

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Which of the following is an input to the Perform Qualitative Risk Analysis process?

A.

Risk register

B.

Risk data quality assessment

C.

Risk categorization

D.

Risk urgency

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Which activity is an input to the Conduct Procurements process?

A.

Organizational process assets

B.

Resource availability

C.

Perform Integrated Change Control

D.

Team performance assessment

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

A.

Define Activities.

B.

Sequence Activities.

C.

Define Scope.

D.

Control Schedule.

The executive committee of a company is reviewing its portfolios. Which of the following would be helpful to evaluate success?

A.

Charter the strategic objectives.

B.

Control environmental changes.

C.

Monitor changes continuously.

D.

Aggregate benefits realization.

Why is tailoring in a project necessary?

A.

Requirements keep changing.

B.

An artifact must be produced.

C.

A tool or technique is required.

D.

Each project is unique.

In a typical project, project managers spend most of their time:

A.

Estimating

B.

Scheduling

C.

Controlling

D.

Communicating

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

A.

exploit

B.

avoid

C.

mitigate

D.

share

Match the method for categorizing stakeholders with its corresponding description

Which roles does the project manager resemble best?

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

A.

Adaptive

B.

Predictive

C.

Incremental

D.

Iterative

A software development team is working on a project to adapt an application to new, government-established data-privacy rules. What factor led to the creation of this project?

A.

Legal requirement

B.

New technology

C.

Social need

D.

Economic change

What is the main purpose of Project Quality Management?

A.

To meet customer requirements by overworking the team

B.

To fulfill project schedule objectives by rushing planned inspections

C.

To fulfill project requirements of both quality and grade

D.

To exceed customer expectations

Which stakeholder approves a project ' s result?

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

A.

Project Risk Management

B.

Project Human Resource Management

C.

Project Scope Management

D.

Project Stakeholder Management

Most experienced project managers know that:

A.

every project requires the use of all processes in the PMBOK® Guide.

B.

there is no single way to manage a project.

C.

project management techniques are risk free.

D.

there is only one way to manage projects successfully.

What does an S-curve from a Monte Carlo analysis show?

A.

Cumulative probability distribution representing probability of achieving a particular outcome

B.

Individual project risks or uncertainties that have the most potential impact on outcome

C.

Best alternative out of the possible solutions, incorporating associated risks and opportunities

D.

Diagram for all project uncertainties and their influence over a period of time

The stakeholder register is an output of:

A.

Identify Stakeholders.

B.

Plan Stakeholder Management.

C.

Control Stakeholder Engagement.

D.

Manage Stakeholder Engagement.

The review of a seller ' s progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

A.

Work performance information.

B.

Inspections and audits.

C.

Payment systems.

D.

Procurement performance reviews.

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Expected monetary value (EMV) is computed by which equation?

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOK®)

In project management, which document is used to start the initial risk identification?

A.

Assumption log

B.

Risk management plan

C.

Risk register

D.

Issue log

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

A.

triangular distribution

B.

tornado diagram

C.

beta distribution

D.

fishbone diagram

A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

A.

Push communication

B.

Pull communication

C.

Interactive communication

D.

Stakeholder communication

The chart below is an example of a:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

A.

0.45

B.

0.56

C.

0.70

D.

1.36

During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three)

A.

End user

B.

Product owner

C.

Subject matter experts (SMEs)

D.

Project sponsor

E.

Project team

Considering a highly dynamic project environment, which approach should the project manager adopt to manage the project team?

A.

A self-organizing approach to increase team focus and maximize collaboration

B.

A virtual team to minimize feeling of isolation and gaps on sharing knowledge

C.

A distributed team to improve tracking progress, productivity, and performance

D.

A norming approach that requires team members to adjust their behavior and work together

The three processes of Project Cost Management are:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

When the business objectives of an organization change, project goals need to be:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Risk exists the moment that a project is:

A.

planned.

B.

conceived.

C.

chartered.

D.

executed.

Due to new market conditions a five-year project......need to be updated

Due to new market conditions a five-year project requires a full revision of project objectives. Which components to the stakeholder engagement plan need to be updated?

A.

Scope and impact of change to stakeholders

B.

Project scope and stakeholders goals

C.

Engagement level of key stakeholders

D.

Stakeholders expectations for the project

What key component of the project charter defines the conditions for dosing a project phase?

A.

Purpose

B.

Approval requirements

C.

Exit criteria

D.

High-level requirements

How can a project manager represent a contingency reserve in the schedule?

A.

Additional weeks of work to account for unknown-unknowns risks

B.

Task duration estimates of the best case scenarios

C.

Addition Duration estimates in response to identified risks that have been accepted

D.

Milestones representing the completion of deliverables

After an internal deliverable review session with the team, the project manager indicates some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and the required network. How would the project manager define extra costs?

A.

Appraisal costs

B.

Management reserves

C.

Cost of nonconformance

D.

Cost of conformance

What behavior refers to leadership style?

A.

Do things right.

B.

Do the right things

C.

Ask how and when.

D.

Rely on control

An input of the Create WBS process is:

A.

requirements documentation.

B.

scope baseline.

C.

project charter.

D.

validated deliverables.

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work.

What should the project manager answer?

A.

Activity level

B.

Deliverable level

C.

Task level

D.

Work package level

When would resource leveling be applied to a schedule model?

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Which of the following techniques should a project manager of a large project with virtual teams use to enhance collaboration?

A.

Resource breakdown structure

B.

Physical resources assignment

C.

Team building activities

D.

Integrated Change Control

Which document can help a project manager to leverage historical project information?

A.

Lessons learned register

B.

Schedule baseline

C.

Work performance data

D.

Deliverable acceptance forms

After winning a large government contract, a company needs to hire a portfolio manager What vital qualification should candidates possess?

A.

Ability to manage strategic goals across multiple projects

B.

Skills to manage a large project

C.

Competency to manage multiple projects that align departments

D.

Capability of managing project schedules

A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.

What should the project manager do to address this issue?

A.

Apply emotional intelligence (El) skills, such as active listening, to understand the team ' s issues.

B.

Instruct the team members to self-organize and resolve any outstanding issues.

C.

Ask the team members to record their concerns in the lessons learned log for future action.

D.

Encourage the team to follow the project plan that was developed with team input.

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

A.

If the operation team members were trained externally

B.

If the transition process was agreed upon during the build

C.

If the end-user documentation was more thorough

D.

If the operations manager was invited to all sprint reviews

Which are the main objectives of Project Risk Management?

A.

Increase the probability of positive risks and decrease the probability of negative risks

B.

Avoid all kind of risks

C.

Increase the probability of positive risks and eliminate all negative risks

D.

Identify positive and negative risks

A project charter is an output of which Process Group?

A.

Executing

B.

Planning

C.

Initiating

D.

Closing