Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

A.

Uniform

B.

Continuous

C.

Discrete

D.

Linear

Which action should a project manager take to ensure that the project management plan is effective and current?

A.

Conduct periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards.

D.

Complete the quality control checklist.

Which tool should a project manager consider to deal with multiple sources of risk?

A.

An updated risk register

B.

Risk breakdown structure

C.

Issue log

D.

Stakeholder register

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

A.

budget at completion (BAC)

B.

earned value management (EVM)

C.

to-complete performance index

D.

cost performance index

Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.

A.

2.0

B.

45

C.

0.5

D.

15

What are the key tools for managing project knowledge?

A.

Expert judgment and data gathering

B.

Networking and storytelling

C.

Data analysis and decision making

D.

Prototypes and product analysis

Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?

A.

Power interest grid

B.

Stakeholder cube

C.

Salience model

D.

Directions of influence

Two members of the team are having a conflict..............or partially resolve the problem

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.

Which technique should the project manager use?

A.

Withdraw/Avoid

B.

Smooth/Accommodate

C.

Compromise/Reconcile

D.

Collaborate/Problem Solve

What are the inputs of the Estimate Costs process?

A.

Project management plan, work performance data, enterprise environmental factors, and organizational process assets

B.

Project management plan, project documents, enterprise environmental factors, and organizational process assets

C.

Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets

D.

Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets

Which is a tool or technique used in Define Scope?

A.

Templates, forms, and standards

B.

Change requests

C.

Product analysis

D.

Project assumptions

Which can be used to convert a verified deliverable to an accepted deliverable?

A.

Decomposition

B.

Reporting

C.

Voting

D.

Brainstorming

The Define Scope process is in which of the following Process Groups?

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

An element of the project scope statement is:

A.

Acceptance criteria.

B.

A stakeholder list.

C.

A summary budget,

D.

High-level risks.

The process of identifying specific actions to be performed to produce project deliverables is:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

A project manager is assigned to a new project with a defined scope. The project requires advanced planning at the start of the project. Which approach should the project manager select for the project?

A.

Predictive

B.

Hybrid

C.

Kanban

D.

Adaptive

A company must implement sales software because it is opening a new branch in a foreign market. Although this software is used in every domestic branch, multiple changes are expected during the implementation because It is a foreign location.

Which type of life cycle would the project manager use in this case?

A.

Predictive life cycle

B.

Waterfall life cycle

C.

Hybrid life cycle

D.

Product life cycle

While executing a building construction project, the supplier may delay the delivery and increase the cost of materials due to new safety regulations. The team has identified an option to absorb the cost by reducing the lag for some of the tasks.

What should the team do to ensure that this situation is managed?

A.

Implement Appropriate Response

B.

Plan Project Risk Management

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

In a project, the cost performance indicator (CPI) is less than 1 and the schedule performance indicator (SPI) is more than 1. What is the status of the project?

A.

The project is over budget and behind schedule.

B.

The project is over budget and ahead of schedule.

C.

The project is under budget and behind schedule.

D.

The project is under budget and ahead of schedule.

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

A.

Historical relationships

B.

Dependency determination

C.

Bottom-up estimating

D.

Rolling wave planning

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?

A.

Initiate change control.

B.

Address risk mitigation.

C.

Escalate this to the project sponsor.

D.

Initiate project closure.

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

What are the formal and informal policies, procedures, and guidelines that could impact how the project ' s scope is managed?

A.

Organizational process assets

B.

Enterprise environmental factors

C.

Project management processes

D.

Project scope management plan

A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?

A.

The risk management plan and the assumption log

B.

Costs estimates and cost forecast

C.

The risk management plan and the basis of estimates

D.

The assumption log and the project charter

One of the tools and techniques of the Manage Project Team process is:

A.

organization charts.

B.

ground rules.

C.

organizational theory,

D.

conflict management.

The features and functions that characterize a result, product, or service can refer to:

A.

project scope

B.

product scope

C.

service scope

D.

product breakdown structure

Which of the following is an information gathering technique in Identify Risks?

A.

Influence diagrams

B.

Brainstorming

C.

Assumption analysis

D.

SWOT analysis

A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?

A.

-12

B.

1.15

C.

38

D.

12

The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.

What equation should the project manager use?

A.

Static payback period = 6 + 1300 / 500 = 6.6

B.

Static payback period = 3 + 1200 / 500 = 5.4

C.

Static payback period = 5 + 700 / 500 = 5.4

D.

Static payback period = 5 + 200 / 500 = 5.4

The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?

A.

10

B.

12

C.

14

D.

16

The process of defining how the project scope will be validated and controlled is known as:

A.

Define Scope.

B.

Develop Project Management Plan.

C.

Plan Scope Management.

D.

Plan Quality Management.

Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?

A.

Internal

B.

External

C.

Discretionary

D.

Mandatory

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

A.

Cost management plan.

B.

Work performance information.

C.

Quality management plan.

D.

Work breakdown structure.

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

A.

work package

B.

deliverable

C.

milestone

D.

activity

An input of the Plan Procurement Management process is:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Which process involves developing an approximation of the monetary resources needed to complete project activities?

A.

Estimate Costs

B.

Control Costs

C.

Determine Budget

D.

Plan Cost Management

In a weak matrix, the project managers role is:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

Agile release planning provides a high-level summary timeline of the release schedule based on.

A.

Activities and story points

B.

Iteration and prioritization plans

C.

Product roadmap and the product vision

D.

Tasks and user stories

Progressively elaborating high-level information into detailed plans is performed by the:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

Which grid shows which resources are tied to work packages?

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Project assignment chart

D.

Personnel assignment matrix

How is the Project Scope Management process different in agile and adaptive projects then in traditional projects?

A.

Less time spent on defining scope early on

B.

More time spent on defining scope early on

C.

Less time spent on scope management process

D.

Project scope management is the same in all projects

In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?

A.

Ensures a thorough unit test case coverage

B.

Ensures an accurate reflection of the stakeholders ' intentions

C.

Ensures that the business problem is solved

D.

Ensures the successful delivery of business value

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?

A.

Project Cost Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Schedule Management

Which is a method of prototyping that creates a functioning representation of the final finished product to the user?

A.

Low-fidelity prototyping

B.

High-fidelity prototyping

C.

Data prototyping

D.

Report prototyping

Which process in Project Time Management includes reserve analysis as a tool or technique?

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

When cost variance is negative and schedule variance is positive, the project is:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

A practitioner organized a requirements workshop with the client ' s frontline application users. The users explained that one of the challenges of the current application is that they must click on each input before entering data, which happens thousands of times a day.

Which technique did the practitioner use to identify this pain point?

A.

System thinking

B.

User acceptance testing

C.

Decision-making

D.

Active listening