Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

A.

Procurement documents

B.

Communications plan

C.

Project charter

D.

Stakeholder register

Which role does the project manager resemble best?

A.

Orchestra conductor

B.

Facilities supervisor

C.

Functional manager

D.

School principal

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

A.

Policies and lessons learned from other projects

B.

Information technology software and employee capability

C.

Resource availability and employee capability

D.

Marketplace conditions and legal restrictions

The Perform Integrated Change Control process occurs in which Process Group?

A.

Initiating

B.

Executing

C.

Monitoring and Controlling

D.

Planning

In a preliminary meeting for a project, team members decide to execute the project with methodology A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?

A.

Use a lightweight cost estimation due to the nature of angile projects.

B.

Use a detailed cost estimation for agile projects.

C.

Retrieve a dudget from a previous project and create a baseline of this project based on it.

D.

Use a detailed work breakdown structure (WBS) to get cost estimation.

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

What is an example of an emerging trend in procurement management?

A.

Online technology enable projects to postpone ordering long lead items until the items are needed

B.

Online technologies allow a project ' s progress to be viewed by all stakeholders to build better relations

C.

Online procurement tools provide buyers with multiple sources to advertise to sellers.

D.

Online procurement tools provide sellers with designated sources for procurement documents and the resources to complete them.

A sponsor asks a project manager to provide a project ' s expected total costs based on its progress. What formula should the project manager use to determine this?

A.

Earned value (EV) / actual cost (AC)

B.

Estimate at completion (EAC) - AC

C.

Budget at completion (BAC) / cost performance index (CPI)

D.

EV - planned value (PV)

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

A.

Interactive

B.

Push

C.

Verbal

D.

Oral

Which are examples of processes that may be used once or at predefined points in the project life cycle?

A.

Develop Project Charter and Close Project or Phase

B.

Define Activities and Acquire Resources

C.

Control Schedule and Conduct Procurements

D.

Monitor Communications and Control Costs

Which tool or technique is used in Close Procurements?

A.

Contract plan

B.

Procurement plan

C.

Closure process

D.

Procurement audits

Which process numerically analyzes the effect of identified risks on overall project objectives?

A.

Plan Risk Management

B.

Plan Risk Responses

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

A.

Checksheets

B.

Histograms

C.

Flowcharts

D.

Control charts

Which is the order of steps in the Procurement Management process?

A.

Identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, contracting with selected vendors, and controlling procurements

B.

Identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, obtaining quotes or proposals, and controlling procurements

C.

Controlling procurements, identifying and planning procurement requirements, obtaining quotes or proposals, negotiating with vendors, and contracting with selected vendors

D.

Obtaining quotes or proposals, identifying and planning procurement requirements, negotiating with vendors, contracting with selected vendors, and controlling procurements

A risk that arises as a direct result of implementing a risk response is called a:

A.

contingent risk

B.

residual risk

C.

potential risk

D.

secondary risk

Which is used to solicit proposals from prospective sellers?

A.

Procurement statement of work

B.

Resource calendars

C.

Procurement document

D.

Independent estimates

Which task will a project manager undertake while conducting Project Resource Management?

A.

Identity the different aspects of me team to manage and control physical resources efficiently.

B.

Procure equipment, materials, facilities, and infrastructure for the project.

C.

Train the team members in project skill sets.

D.

Define the roles and responsibilities of each team member.

In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from recurring?

A.

Extend the delivery time for the product since the management reserve allows it.

B.

Temporarily use another team for the next iteration and evaluate their performance.

C.

Observe the project team ' s performance for the next two iterations before taking any action.

D.

Identify possible reasons for the delay and consult the risk register for corrective actions.

Enterprise environmental factors are an input to which process?

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Which of the following documents allows the project manager to assess risks that may require near term action?

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

An organization that is being interviewed online has recently experienced a severe network outage. Consequently, the organization has stated that it is required to have a working data network.

Which classification should be assigned to data network requirements?

A.

Customer requirement

B.

Transition requirement

C.

Solution requirement

D.

Business requirement

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

A.

Direct

B.

Interactive

C.

Pull

D.

Push

When a dynamic systems development method (DSDM) practitioner receives a new high-priority feature request, what should the practitioner do first?

A.

Develop the feature as a parallel work package.

B.

Shorten the current work period and begin the new work.

C.

Ask a dedicated team member to complete it immediately.

D.

Prioritize it in the requirements list for the next work period.

Who should the stakeholders consult to discuss concerns about the current work package?

A.

Project manager

B.

Business analyst

C.

Project coordinator

D.

Project sponsor

A stakeholder asked the project manager to add an additional feature to the project scope. The project manager is unsure whether the project budget will allow this additional scope.

What component of the project management plan should the project manager reference to determine whether the budget will allow a new feature to be added?

A.

Risk management plan

B.

Cost estimate

C.

Risk register

D.

Cost management plan

The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?

A.

Monitor Communications

B.

Plan Communications Management

C.

Manage Communications

D.

Manage Stakeholder Engagement

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

Technical capability, past performance, and intellectual property rights are examples of:

A.

performance measurement criteria

B.

source selection criteria

C.

product acceptance criteria

D.

phase exit criteria

What can a project1 manager review to understand the status of project?

A.

Work breakdown structure (WBS) status

B.

Quality and technical performance measures

C.

Cost and scope baselines

D.

Business case completeness

An input to the Estimate Activity Resources process is:

A.

Activity resource requirements.

B.

Published estimating data.

C.

Resource calendars.

D.

Resource breakdown structure (RBS).

Resource calendars are included in the:

A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

What can the cost management plan be established?

A.

Cost baseline

B.

Cost estimates

C.

Basis of estimates

D.

Control thresholds

Which of the following is an example of an internal factor that influences the outcome of the project?

A.

Legal restrictions

B.

Financial considerations

C.

Commercial database

D.

Geographic distribution of facilities

Which of the following is an output of the Perform Integrated Change Control process?

A.

Cost-benefit analysis

B.

Updated project charter

C.

Approved change request

D.

Multicriteria decision analysis

What is the purpose of the project schedule management.

A.

Estimates specific time and the deadline when the products, services and results will be delivered.

B.

Determines in details the resources and time that each task will require to be done

C.

Represents how and when the project will deliver the results defined in the project scope.

D.

It provides the relationships among the project activities and their risks.

When should Project Risk Management be conducted?

A.

Project Planning

B.

Monitoring and Controlling

C.

Quality Planning

D.

Throughout the project lifecycle

A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?

A.

Resource management plan and lessons learned register

B.

Resource management plan and cost baseline

C.

Resource management plan and procurement management plan

D.

Resource management plan and preassignment

A project manager has reached an agreement on the requirements and now needs to define the workflow for the end user. A critical step must be completed and validated by the end user before proceeding.

Which modeling tool best describes this process?

A.

Traceability

B.

User interface design

C.

Use case

D.

Wireframe

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

A.

Approved change requests

B.

Verified deliverables

C.

Lessons learned

D.

Work performance data

When can we say that a project is completed?

A.

When the planned time duration is completed

B.

When the project objectives have been reached

C.

When the project manager has left the team

D.

When the project team decides to stop the work on the project

The procurement process that documents agreements and related documentation for future reference is known as:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Typical outcomes of a project include:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members know their roles and responsibilities. What are the four elements of a RACI chart?

A.

Recommend, accountable, consult, and inform

B.

Responsible, accountable, consult, and inform

C.

Recommend, approve, coordinate, and inform

D.

Responsible, accountable, coordinate, and inform

In adaptive projects, who should approve the prioritization of the backlog?

A.

Project manager

B.

Project sponsor

C.

Business analyst

D.

Product owner

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Which additional considerations should the project manager make when managing risks in an agile/adaptive project?

A.

Add more risk categories

B.

Identify, analyze, and manage risk during each iteration of the project

C.

Add new values to the probability and impact matrix

D.

Increase the reserves because of the high variability environment

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

A.

Verified deliverables

B.

Validated deliverables

C.

Accepted deliverables

D.

Completed change requests