Which of the following is a tool and technique used to monitor risk?
During project selection, which factor is most important?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
What are the identified risks for doing excessive decomposition in a WBS?
An input to the Estimate Activity Resources process is:
The total of the planned value (PV) is also known as:
The process for performing variance analysis may vary, depending on:
Which process requires implementation of approved changes?
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
Activity cost estimates are quantitative assessments of the probable costs required to:
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
A tool and technique used during the Define Scope process is:
The completion of the project scope is measured against the:
What happens to a stakeholder's project influence over time?
One of the objectives of a quality audit is to:
A tool and technique used during the Collect Requirements process is:
Inputs to the Plan Risk Management process include the:
Which of the following is an output of Define Scope?
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
Which technique is utilized in the Control Schedule process?
Prototype development may be used as a tool for which of the following risk response strategies?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
A project lifecycle is defined as:
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
Which of the following is a tool or technique used in the Acquire Project Team process?
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
The process of identifying specific actions to be performed to produce project deliverables is:
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
Which risk response strategy is common for both positive and negative risks?
Which activity may occur at project or phase closure?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
The risk shared between the buyer and seller is determined by the:
After Define Activities and Sequence Activities, the next process is:
Expected monetary value (EMV) is computed by which equation?
Projects are separated into phases or subprojects; these phases include:
The process to ensure that appropriate quality standards and operational definitions are used is:
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
In which process is a project manager identified and given the authority to apply resources to project activities?
Which tool and technique is used in Conduct Procurements?
Which of the following factors is lowest at the start of the project?
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Which of the following is an example of schedule compression?
What is the most accurate rough order of magnitude (ROM)?
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
Another name for an Ishikawa diagram is:
What does a CPI value greater than 1.0 indicate?
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?