Two members of the team are having a conflict..............or partially resolve the problem
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties, in order to temporarily or partially resolve the problem.
Which technique should the project manager use?
Which of these is true project integration management?
Which is the appropriate tool to identify the possible correlation two elements in aprocess?
When can we say that a project is completed?
Which tools and techniques should a project manager use to monitor risks?
After defining activities in project schedule management, which processes should a project manager follow?
Which of the following items is a technique for data gathering?
A team is feeling pressured to begin development work due to tight project deadlines. There are stakeholders with similar functions located in multiple countries. To accelerate the process, the business analyst has limited the requirements elicitation sessions to times that work for stakeholders in one time zone. To reduce the risk with this approach, which step should the business analyst take?
A project is composed of three phases that are implemented in parallel without affecting one another. The baselines for each individual phase have been approved by the major stakeholders, and there is a minimal ability to vary the baselines during the execution of the project.
Which methodology did the project manager adopt?
In the business analysis aspect of a construction project, what is the purpose of the requirements validation process?
A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The manager of the business unit that will use the new product is asking for additional functionality before approving the rollout for their team.
What should the project manager do next?
To ensure stakeholder satisfaction; identified stakeholder needs should all be
What should be the frequency for meetings when transitioning from Scrum to Kanban?
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?
During a retrospective, the team finds that all of the user stories are not complete. What should be done with the incomplete user stories?
In one of the project meetings during a project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
Select three processes that are associated with Project Schedule Management.
As the project takes place and some issues arose, the project manager (Joe) finds out that some team members were not 100% committed to the project, and some of them were underperforming.
What should the project manager have done to avoid this situation?
It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?
A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?
The project manager has following information about duration for an activity:
* Most likely [tM] - 15 days
* Pessimistic [tP] - 20 days
* Optimistic [tO] - 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
Project governance refers to framework.......which of the following is a portfolio?
Pioject governance refers lo framework, functions, and processes that guide project management activates with a defined hierarchy between projects, programs and poctfotos. According to this hierarchy, which ot Die following is a portfolio?
Which is an aspect of the requirements management plan?
An adaptive team's velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project.
How should the project manager calculate the anticipated velocity for future sprints?
A project team is tasked with decomposing the scope to enable detailed cost and duration estimates. What should the team do to achieve this requirement?
A project manager is responsible for delivering new software for their company. Based on previous experiences, the project manager decides to use the dynamic systems development method (DSDM). The project manager will use this method to prioritize the scope to meet project constraints.
Which elements are included in the DSDM framework?
All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?
Match each Project Cost Management process with its appropriate keyword
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take to account for risk management n this environment’
A construction project is underway with three months left to complete the building. A public authority responsible for approving the final stage is stalling the project. What should the project manager do?
Which actions should a project manager follow to manage stakeholders?
A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements. What should the business analyst do?
When executing a project, a recently hired subject matter expert (SME) who reviewed the execution progress remarked that the schedule could be crashed and that the schedule was not assessed properly. What should the project manager do next?
Construction of a building has stopped due to a supplier's failure to deliver concrete. The project schedule is behind by three months. What should the project manager do to overcome this problem and put the project back on track?
A key project team member complains about being left out of the communication loop. In order to ensure that each key member is involved, who should review the business analysis communications management plan?
A tool and technique used during the Perform Qualitative Risk Analysis process is:
Which tool and technique is used in Conduct Procurements?
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?
Which activity involves ensuring that the composition of a projects configuration items is correct?
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
Which of the following is an input to the Perform Qualitative Risk Analysis process?
Which process should be conducted from the project inception through completion?
"Tailoring" is defined as the:
Monte Carlo is which type of risk analysis technique?
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:
Which standard has interrelationships to other project management disciplines such as program management and portfolio management?
What provides information regarding the ways people, teams, and organizational units behave?
Which piece of information is part of the WBS Dictionary?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?