Which of the following is an input to the Direct and Manage Project Execution process?
Which of the following characteristics are found in a functional organizational structure?
Which tool or technique is used in Close Procurements?
How many Project Management Process Groups are there?
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
Which process involves identifying and documenting the logical relationships between project activities?
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
Which of the following project documents is an input to the Control Scope process?
Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
The progressive detailing of the project management plan is called:
Which cost estimate technique includes contingencies to account for cost uncertainty?
What does a CPI value greater than 1.0 indicate?
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
In which process might a project manager use risk reassessment as a tool and technique?
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
Which process determines the risks that might affect the project?
In Project Cost Management, which input is exclusive to the Determine Budget process?
Which of the following reduces the probability of potential consequences of project risk events?
Which tool or technique is used in Manage Stakeholder Expectations?
Which of the following are outputs of Develop Project Team?
In which Project Management Process Group is the project charter developed?
Which of the following is an input to Develop Human Resource Plan?
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
Which Process Group contains those processes performed to define a new project?
Project contracts generally fall into which of the following three broad categories?
Lessons learned documentation is gathered during which of the following Project Management Process Groups?
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
The process of identifying the stakeholders' information needs is completed during:
What is a tool to improve team performance?
Which of the following documents allows the project manager to assess risks that may require near term action?
In which Process Group are lessons learned documented?
Which can be used to determine whether a process is stable or has predictable performance?
What type of project structure is a hierarchically organized depiction of the resources by type?
What is the number of stakeholders, if the project has 28 potential communication channels?
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?
Which activity is an input to the Conduct Procurements process?
A procurement management plan is a subsidiary of which other type of plan?
When can pre-assignment of project team members occur?
Which is a tool or technique used in Define Scope?
The scope of a project cannot be defined without some basic understanding of how to create the specified: