The three processes of Project Cost Management are:
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
Who determines which dependencies are mandatory during the Sequence Activities process?
The cost benefit analysis tool is used for creating:
Which of the following can be used as an input for Define Scope?
An input to the Estimate Activity Resources process is:
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
Activity cost estimates are quantitative assessments of the probable costs required to:
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
What is project management?
What are the identified risks for doing excessive decomposition in a WBS?
At the end of the project, what will be the value of SV?
The total of the planned value (PV) is also known as:
Which of the following is an output of the Conduct Procurements process?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which activity may occur at project or phase closure?
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
Which of the following is a tool and technique used to monitor risk?
Which risk response strategy is common for both positive and negative risks?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
Resource calendars are included in the:
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?
The initial development of a Project Scope Management plan uses which technique?
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
Which of the following is a group decision-making technique?
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
Which of the following are three inputs to the risk register?
The completion of the project scope is measured against the:
Which is one of the determining factors used to calculate CPI?
Which input will be used when tasked with developing the human resource plan?
During project selection, which factor is most important?
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
Projects are separated into phases or subprojects; these phases include:
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Which of the following is a tool or technique used in the Acquire Project Team process?
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
The process for performing variance analysis may vary, depending on:
Which technique is utilized in the Control Schedule process?
Prototype development may be used as a tool for which of the following risk response strategies?