Which of the following is the MOST important reason for establishing and maintaining a supplier quality certification program?

A.

Quality champions from both the buyer and seller will have better opportunities to communicate.

B.

Supplier payments should be closely tied to maintaining quality standards.

C.

A supplier quality certification program is necessary for the development of a supplier scorecard.

D.

Certification programs keep suppliers focused on quality elements important to the customer.

According to Six Sigma methodology, what percentage of parts should be free from manufacturing defects?

A.

99%

B.

100%

C.

99.99966%

D.

99.66666%

A manufacturer is updating its production plans for the remainder of the year. The firm has already obtained revised needs information from its customers, as well as the finance and sales teams. Which of the following additional information would be MOST useful to the firm?

A.

Upcoming promotions from the marketing team

B.

Recent production issues from the quality team

C.

Product modifications from the design team

D.

Corporate goals from the management team

A graph of a firm’s inventory replenishment system reveals the following:

Which of the following is TRUE’

A.

The order cycle is two and a half days.

B.

The average inventory is 1,850 units.

C.

There is a fixed order quantity of 500 units.

D.

There is near instantaneous replenishment.

Which of the following is the PRIMARY benefit of project governance?

A.

Projects considered essential are prioritized over others already in progress.

B.

Business projects need less monitoring, which allows local managers freedom to execute their projects.

C.

Projects that are behind targets may be allowed to continue, if the cause of the delay can be resolved.

D.

Business cases and associated benefits are subject to effective scrutiny, which helps with setting project timelines.

Which of the following is the FIRST stage in the Retail Event Collaboration Process Overview (VICS CPFR Model)?

A.

Execution

B.

Strategy and planning

C.

Analysis

D.

Demand and supply management

The packaging optimization process begins by understanding which of the following?

A.

Product characteristics

B.

Packaging density

C.

Transportation modes

D.

Packaging budget

XYZ, Inc. notices that one of its suppliers has been failing to achieve on-time delivery, even though XYZ sends it a 6-month projected order forecast every month. The supplier claims that it takes nine months to receive important raw materials, and that this causes the poor delivery performance. Nevertheless, XYZ must continue purchasing from this supplier, as it is a sole supplier. Given this situation, which of following is the BEST course of action for XYZ to take?

A.

Send the 6-month forecast data weekly instead of monthly to the supplier, and request it purchase raw materials based on the projections

B.

Request that the supplier submit an open order report on a weekly basis with details on the latest shipment status

C.

Discuss the issue with engineering to determine if the firm can use different raw materials to manufacture the product

D.

Extend the forecast timeline from six months to one year, and request the supplier purchase raw materials based on the projections

A firm completes its near level production, five-month demand plan for the next business planning cycle:

Month 1Month 2Month 3Month 4Month 5

Demand Forecast15,00020,00025,00025,00018,000

Production Plan (Regular Time)20,00020,00020,00020,00018,000

Production Plan (Overtime)5,000

Ending Inventory5,0005,000

Average Inventory2,5005,0002,500

Workforce PlanningStarting WorkforceMonth 1Month 2Month 3Month 4Month 5

Hires7

Layoffs2

Actual Workforce Size132020202018

Regular Time Hours Required2,0002,0002,0002,0001,800

Overtime Hours Required500

Costs

Regular time cost per unit$15

Overtime cost per unitS25

Monthly inventory cost per unit$1

Cost of hire$1,500

Cost of layoffS400

What is the cost of this demand plan?

A.

$1,605,000

B.

$180,800

C.

$1,606,300

D.

$1,616,300

Which of the following BEST explains why forecast accuracy is important in contracts with suppliers?

A.

It locks in the lowest possible cost to the organization over the life of the contract.

B.

. It allows the buying firm to gauge supplier performance degradation over the life of the contract.

C.

It improves continuity of supply while allowing the supplier to reduce costs over time.

D.

It allows the organization more freedom in procuring supply in the market.