Select which option best completes the following statement: _____________ is all about response to change.

A.

Change management

B.

Planning

C.

Customer satisfaction

D.

Agile

Who is required to attend the Daily Scrum?

A.

Scrum Master

B.

Development Team

C.

Development Team and Product Owner

D.

Development Team and Scrum Master

Which statement below best describes the primary objective of the Sprint Review?

A.

The primary objective of the Sprint Review is to demo the Sprint work for Senior Management

B.

The primary objective of the Sprint Review is to demo the Sprint work and to receive feedback from the Product Owner(s) on the work completed in the Sprint

C.

The primary objective of the Sprint Review is to demo the Sprint work and to receive feedback from the Scrum Mater on the work completed in the Sprint

D.

The primary objective of the Sprint Review is to demo the Sprint work and to recommend ways to work better in the Sprint.

Which of the following are the two features of the Scrum Teams? (Choose two.)

A.

Rules of Etiquette

B.

Cross-functional

C.

Process Oriented

D.

Can have multiple Product Owner’s

What is an ideal size for a Scrum team?

A.

13

B.

4

C.

7

D.

10

When is the Sprint Backlog created?

A.

At the beginning of the project

B.

Prior to the Sprint Planning meeting

C.

During the Sprint

D.

During the Sprint Planning meeting

_____________ can change the priority of items in the _________ backlog at any time.

A.

The Team; Product

B.

The Product Owner(s); Sprint

C.

The Product Owner(s); Product

D.

The Scrum Master; Sprint

Which of the following statements best explains what the term Sprint means in Scrum?

A.

A sprint is a specific amount of days for a team to test and resolve any issues prior to product release or shipment

B.

A sprint is a specific amount of days for a team to work at a sustainable pace to finish select work.

C.

A sprint is an agreed upon period of time for team members to select individual items from the product backlog to work on.

D.

A sprint is a specific amount of days for a team to work as many hours as needed to finish assigned work

Which of the following is not reflected in a Sprint Burn down Chart?

A.

Total Days in Sprint

B.

Number of Tasks Remaining

C.

Day of Sprint

D.

Work Hours Remaining

True or False: The sprint planning is a one-day time boxed meeting divided into two 4-hour sessions?

A.

True

B.

False