You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

A.

The development team should negotiate with the Product Owner on the definition of "done".

B.

The development team should work the extra 8 hours to complete their commitment to the Product Owner

C.

The development team should place the two Product Backlog items back onto the Product Backlog

D.

The development team should keep the three tasks on the Sprint Backlog for the next Sprint and complete those tasks first

Which of the following is a role in the Scrum framework?

A.

Team

B.

System Administrator

C.

Software Tester

D.

Scrum Developer

What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity?

A.

By ensuring the meetings start and end at the proper time

B.

By facilitating Development Team decisions and removing impediments

C.

By preventing changes to the Backlog once the Sprint begins

D.

By keeping high value features high in the Product Backlog

A _____________________ is created during the first half of the Sprint planning meeting and a

_________________ is created during the second half of the Sprint planning meeting?

A.

Sprint Backlog, collection of tasks

B.

Product Backlog, collection of tasks

C.

Sprint Goal, Sprint Backlog

D.

Product Backlog, Sprint Backlog

The Sprint Goal is selected before the Sprint Backlog is created.

A.

True

B.

False

It's come to your attention that some team members feel that Carlos is a negative influence on the team. You can certainly understand why — he believes that everything is doomed. What should you do?

A.

Remove Carlos from the team.

B.

Use Carlos as an asset, particularly during risk identification

C.

Ignore him and hope it goes away

D.

Escalate the issue with the higher authorities

What is the maximum amount of time a sprint retrospective should take?

A.

1 hour

B.

1 and half hour

C.

3 hours, for an 30 days Sprint

Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?

A.

The development team cannot meet their Sprint commitment to complete work if requirements are changing

B.

A Sprint cycle is not enough time for senior management review and approve changes

C.

This forces Product Owners to focus on what is really important for the team to develop.

D.

The development team must be able to limit the Product Owner authority

Who determines whether the development team has been assigned enough work in a Sprint?

A.

The Development Team

B.

The Product Owner

C.

The Product Owner and the Scrum Master

D.

The Scrum Master

The term Agile Development was first introduced in:

A.

An addendum called Project Management Principles

B.

The Agile Manifesto

C.

Lean Process Improvement

D.

The Scrum Framework