True or False: Scrum mandates the use of burndown charts.

A.

True

B.

False

True or False: In the Sprint Review, the Product Backlog is re-prioritized by the stakeholders.

A.

True

B.

False

Who is responsible for clearly expressing Product Backlog Items? (Choose the best answer)

A.

The Product Owner.

B.

The Scrum Master.

C.

The Scrum Master, or the Scrum Master may have the Developers do it.

D.

The business analyst who represents the Product Owner in the Developers.

As the Sprint Planning meeting progresses, the Developers see that the workload is greater than they can handle. Which two are valid actions? (Choose the best two answers)

A.

The Developers work overtime during this Sprint.

B.

Recruit additional Developers before the work can begin.

C.

Cancel the Sprint.

D.

Remove or change selected Product Backlog items.

E.

The Developers ensure that the Product Owner is aware, start the Sprint, and monitor progress.