Which three purposes does the Definition of "Done" serve? (Choose the best three answers)

A.

Increase transparency.

B.

Create a shared understanding of when work is complete.

C.

Describe the work that must be done before the Sprint is allowed to end.

D.

Describe the purpose, objective, and time-box of each Scrum event.

E.

Guide the Developers on how many Product Backlog items to select for the Sprint.

What does it mean to say that an event has a time-box?

A.

The event must happen at a set time.

B.

The event must happen by a given time.

C.

The event must take at least a minimum amount of time.

D.

The event can take no more than a maximum amount of time.

What two things best help the Product Owner manage the value of a product? (Choose the best two answers)

A.

Setting value on individual Product Backlog items using Value Poker.

B.

Devising a formula for a neutral calculation of value.

C.

The order of the Product Backlog.

D.

Validating assumptions of value through frequent releases.

During a Sprint Retrospective, for what is the Scrum Master responsible? (Choose the best answer)

A.

Acting as a scribe to capture the Developers’ answers.

B.

Prioritizing the resulting action items.

C.

Participating as a Scrum Team member and facilitating as requested or needed.

D.

Summarizing and reporting the discussions to management.

Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose the best two answers)

A.

How the team does its work

B.

Team relations

C.

Definition of "Done"

D.

Sprint Backlog for the next Sprint

E.

The value of work currently represented in the Product Backlog

True or False: The Product Owner is an optional attendee of the Sprint Retrospective.

A.

True

B.

False

True or False: Management does not have a role within Scrum.

A.

True

B.

False

Must the Product Owner be present at the Sprint Retrospective? (Choose the best answer)

A.

It is optional. Attendance is only required when the Product Owner gets invited by the Scrum Master.

B.

It is mandatory. The Sprint Retrospective is an opportunity for the Scrum Team to assess its performance and improve itself.

C.

It is not allowed. The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself.

How can a Product Owner use time-boxed Sprints to obtain feedback from users and the market? (Choose the best answer)

A.

Through the assurance that a Developers finishes all work on the Sprint Backlog.

B.

Through frequent delivery of Increments of the product into the market.

C.

By making sure a Sprint does not stop until all testing is done, and the work is verified by the Product Owner.

D.

At the end of each Sprint, a detailed report with all test cases and test results is available.

E.

A business analyst represents the Product Owner to make decisions on his behalf during the Sprint. This way the Product Owner can accept the work at the Sprint Review without further involvement.

Which statement is least accurate when providing a definition of "Done"? (Choose the best answer)

A.

It is the exit criteria to determine whether a Product Backlog item is complete

B.

It may vary depending on the project

C.

It is defined by the Scrum Master

D.

It becomes more complete over time