Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?

A.

A declaration of joint and several liability

B.

A bank guarantee

C.

A surety bond

D.

A parent company guarantee

Towards the end of implementing a varied work (initiated originally by the Contractor as a "Value Engineering Proposal", relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation? [FIDIC Red Book, 2017 Edition]

Choose all of the correct answers (multiple possibilities).

A.

Since the design was approved by the Engineer, the Contractor might not be found responsible for such discrepancy, hence, to be fully compensated.

B.

In this situation, the whole of the varied works should be removed, and the original technical content reinstated.

C.

The Contractor shall immediately rectify, ensuring, that the varied work fully complies with the prevailing standards.

D.

In case it is necessary, the Contractor shall prepare designs for works subject to the Value Engineering, hence, it is up to the Contractor to ensure that the works are fit for the purposes, including that the designs are correct, regardless of any approval or "no-objection" of the Engineer.

Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?

Choose all of the correct answers (multiple possibilities)

A.

All internationally recognized holiday periods.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

Only the delivery dates of Plant and Materials which have not been delivered on Site yet.

When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition 1999)?

A.

Without undue delay after the issuance of the Taking-Over Certificate.

B.

Without undue delay after the issuance of the Performance Certificate.

C.

Within 21 days after the issuance of the Taking-Over Certificate.

D.

Within 21 days after the issuance of the Performance Certificate.

Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?

Choose all of the correct answers (multiple possibilities)

A.

The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor's Cost.

B.

The Engineer cannot sell or otherwise dispose any remaining items and reinstate the Site at the Contractor's Cost.

C.

The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor's items on the Site.

D.

The Employer cannot reinstate and clear the Site and dispose the remaining Contractor's items on the Site if the Contractor fails, as this is the Contractor's obligation.

Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?

A.

"The Employer obtains the best value for money" AND "Disputes should be avoided to the extent achievable."

B.

"Only the Employer should be the one to obtain the best value for money" AND "The Contractor/Subcontractor is paid adequately and timely in accordance with the Contract to maintain its cash flow."

C.

"The Contractor/Subcontractor is paid adequately and in a timely manner in accordance with the Contract to maintain its cash flow" AND "The terms of the Contract are comprehensive and fair to primarily the Employer".

D.

"The Contractor should take advantage of its bargaining power every time possible" AND "Disputes are avoided to the extent achievable, minimised when they do arise, and resolved efficiently."

You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months.

The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.

1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.

The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.

What is the correct Commencement Date?

A.

12 June 2022

B.

15 June 2022

C.

15 July 2022

D.

1 August 2022

You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer's financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?

A.

A prolonged suspension for more than 1 year has affected the whole of the Works.

B.

The Contractor does not receive the amount due under the latest Payment Certificate for more than 4 months after the due date.

C.

The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.

D.

The Employer failed to comply with a final and binding determination issued by the Engineer, and such failure constitutes a material breach of the Employer's obligations under the Contract.

Which one statement regarding the adjustment of the Contract Price as mentioned in Sub-Clause 13.8 of FIDIC Silver Book (edition 1999) is correct?

A.

If the Contract Price is to be adjusted for rises and falls in the cost of labour, the Contractor is entitled to compensation in such a way that all rises and falls in the costs are compensated fully.

B.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. This can result in lower adjustments of the Contract Price than the actual changes in the costs of labour and/or Goods.

C.

If Particular Conditions provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8, it can only apply to rises or falls in the costs of labour and Goods.

D.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. Only the Base Date can be taken as the date from which the adjustment should be calculated from.

You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?

A.

Delay Damages is intended to provide full compensation to the Employer for all damages that it is expected to suffer as a result of the delay.

B.

Delay Damages is intended to be treated as an incentive for the Contractor to perform on time.

C.

Delay Damages is not intended to remove burden for the Employer to demonstrate and prove that it has suffered any loss or damage.

D.

None of the above.