Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?

Choose all of the correct answers (multiple possibilities).

A.

If the advance payment is not completely repaid before Time for Completion.

B.

If advance payment is not completely repaid before the Performance Certificate is issued.

C.

If the advance payment is not completely repaid before the Taking-Over Certificate is issued.

D.

If the advance payment is not completely repaid before termination of the Contract.

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

(Which two answers show characteristics of Test on Completion or Test After Completion under the FIDIC Silver Book (edition 1999)?

Choose all of the correct answers (multiple possibilities).)

A.

In case of failure of the Test on Completion, the Employer may accept the Works, thereby reducing the Contract Price.

B.

The Employer can either opt for Tests on Completion or Tests after Completion, but not both.

C.

Tests after Completion are carried out by the Employer.

D.

Although Tests after Completion fail, it may be considered as passed when performance damages specified in the contract are paid by the Contractor.

Regarding the FIDIC Red Book (edition 1999), which two statements are true?

A.

In emergency situations notices can also be submitted verbally (rather than (also) in writing).

B.

A notice is to be signed by the Engineer, Contractor ' s Representative or Employer ' s Authorised Representative.

C.

A notice and other communications may be delivered by hand, courier and mail. In each case with proof of receipt is required to qualify as legally valid.

D.

Notices and other communications may be sent in hand written, type written, in print or through an electronic original transmission system.

(Which two of the following items are new features introduced in FIDIC Red and Yellow Books (edition 2017) in respect to the procedures relating to the Programme?

Choose all of the correct answers (multiple possibilities).)

A.

The requirement to submit a revised programme by the Contractor whenever the previous programme is inconsistent with actual progress.

B.

Specifying the programming software that shall be used by the Contractor in preparation of the Programme.

C.

The requirement that any revised programmes to be submitted by the Contractor is to reflect accurately the actual progress of the works.

D.

Submission by the Contractor of a detailed time Programme to the Engineer within 28 days after receiving the notice under Sub-Clause 8.1.

FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

A.

True

B.

False

Which of the following form a Contractor ' s entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

A.

Right after the expiry of the payment deadline, the Contractor may terminate the contract.

B.

If the payment is not made within the time period required, after the expiry of such period, from the next day onwards, the Contractor is entitled to suspend all his/her activities on Site.

C.

In case the Employer paid the Contractor late, the Contractor becomes entitled to receive financing charges applying the % included in the Contract Data (if this is not stated, then applying the percentage as included under the corresponding Sub-Clause).

D.

The Contractor is entitled to suspend the works or reduce the rate of progress of the work, after giving a due Notice (21 days) about this intention.

E.

Beyond receiving the financing charges, the Contractor has no further entitlements in such a case.

There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.

Which two of the following statements are NOT applicable reasons?

(Choose all correct answers — multiple possibilities)

A.

Delay the execution of the Works or a Section.

B.

Decrease the Contract Price.

C.

Adversely affect the work of the Contractor ' s Personnel.

D.

Increase the performance of the Works when completed.

(In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer’s Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)

A.

This is an Employer’s Risk under Sub-Clause 17.3 (a)/(b), and the Contractor is entitled to EOT and Cost. The Engineer will assess actual entitlement after the event; no further notices are required.

B.

Violence is an Employer’s Risk; however, the Contractor can only claim after the situation ends. The Engineer cannot determine EOT or Cost yet, and the Contractor must submit a fully detailed claim later.

C.

The Contractor should have foreseen such risks due to the region’s history; therefore, Clause 19 is not applicable.

D.

The Employer is in breach of its obligation to provide safe working conditions under Sub-Clause 2.1; therefore, the Contractor can claim on that basis.

Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?

A.

The Provisional Sum cannot be issued by instruction either by the Engineer (or Employer in case of FIDIC Silver Book).

B.

The Contractor shall, when required by the Engineer, produce proof to substantiate how it has used the Provisional Sum.

C.

Each Provisional Sum shall not be used, in whole or in part, in accordance with instructions from the Engineer.