New Year Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

The FIDIC Books are evolutions of earlier contract models, and although the different versions of a specific model are not the same, familiarity in definitions and structure makes it easier to work with different FIDIC books as well as with their different editions.

Is this statement true or false?

A.

True

B.

False

Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?

A.

Yes

B.

No

Regarding the FIDIC Red Book (edition 1999): which two statements are true in respect of Building Information Modelling (BIM)?

Choose all of the correct answers (multiple possibilities).

A.

General Conditions of Contract require the use of BIM.

B.

BIM is one of the digital data technologies used in all aspects of project planning, investigation, design, construction and operation.

C.

BIM is not related to the improvement of quality, accuracy, delivery times and cost savings.

D.

For construction or building projects involving BIM, many Sub-Clauses of FIDIC Red Book (edition 2017) should be thoroughly reviewed when drafting the Particular Conditions.

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor's reporting requirement end?

A.

After issuance of the Taking-Over Certificate.

B.

After issuance of the Performance Certificate.

C.

At the Date of Completion of the Works (irrespective of whether there is minor outstanding work to be performed).

D.

Until all outstanding works as stated in the Taking-Over Certificate are completed.

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.

A.

True

B.

False

Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?

A.

The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.

B.

The General Conditions allocate the risks between the parties on a fair and equitable basis.

C.

A disproportionate amount of risks is allocated to the Contractor under the General Conditions.

D.

The Contractor provides plant and designs (except as otherwise specified) and executes the other works, all in accordance with the Contract, which includes its Proposal and the Employer's Requirements.

Under the FIDIC Red Book, which one of the following statements is correct for a claim by the Contractor?

A.

The Employer has the authority to accept a claim by the Contractor, even in the case of the Contractor's failure to comply with the notice requirements.

B.

If the Engineer does not make a determination, the Employer and the Contractor are unable to agree to settle an issue that gave rise to a claim.

C.

The Engineer's response to the Contractor's submission of detailed particulars that are required by the procedure for claims by the Contractor must include the Engineer's final decision on the quantum.

D.

It is the Employer's Representative who must first respond to the claim by the Contractor.

E.

The Engineer's response to a claim by the Contractor is final and binding upon the Employer.

The Contractor is entitled to an advance payment. Applying FIDIC Red Book (edition 1999), which two of the following statements are correct?

Choose all of the correct answers (multiple possibilities):

A.

The advance payment is to help the Contractor to finance some of its early cost and expenditure until it becomes entitled to first (non-interim) payment.

B.

The advance payment reflects the amount of works the Contractor has already performed up to the moment such advance payment is performed.

C.

Under the General Conditions, the amount of advance payment is to be paid in full by the Employer through one instalment.

D.

Under the General Conditions, the advance payment will be repaid by deducting all amounts from invoices until the entire advance payment is repaid.

You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?

A.

The Contractor submits a Value Engineering proposal, in which it proposed to change the colour of the outdoor paint. The Engineer approved the proposal.

B.

The Engineer instructs a change in slopes of stairs to the parking lot with an Instruction in accordance with Sub-Clause 3.3.

C.

The Engineer requests a proposal regarding a change in type of windows and doors of the business centre.

D.

The Employer verbally instructs a change in the layout of the rooftop restaurant. The Engineer issued an Instruction describing the required change with revised design drawings.

There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.

Which two of the following statements areNOTapplicable reasons?

(Choose all correct answers — multiple possibilities)

A.

Delay the execution of the Works or a Section.

B.

Decrease the Contract Price.

C.

Adversely affect the work of the Contractor's Personnel.

D.

Increase the performance of the Works when completed.