Which of the following BEST illustrates how team members with different roles should interact on the team?

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

A.

Project status report

B.

Project evaluation review

C.

Project management software

D.

Requirements traceability matrix

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

A.

The project utilized all of its available reserve.

B.

The project has scope creep.

C.

The project deviated from the critical path.

D.

The project is trending ahead of schedule.

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

A PM is working to establish accepted communication channels and to define access requirements. In which of the following phases is the project?

A.

Discovery

B.

Execution

C.

Initiating

D.

Planning

Which of the following requires the MOST availability from the business team?

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

A quality assurance team is based in three different locations To validate the project deliverables, a project manager sent the hardware for testing purposes to the team in each of the locations. Two teams confirmed the hardware arrived, but one group did not receive it because of local customs Which of the following ESG factors is the project team facing?

A.

Awareness of the company vision, mission statement, and values

B.

Impact of the project on the company's brand value

C.

Awareness of applicable regulations and standards

D.

Impact of the project on the local and global environments

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

A.

Escalate directly to the project sponsor

B.

Push the kickoff meeting out by one week

C.

Proceed with the kickoff as planned

D.

Identity replacements for project stakeholders

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

A.

Add a new risk.

B.

Perform an impact analysis.

C.

Escalate to the sponsor.

D.

Raise a change request.

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

A.

Flat

B.

Projectized

C.

Weak matrix

D.

Functional