During a brainstorming session, a team member expressed concerns that solar flares could cause intermittent outages for those individuals working on the project. Which of the following would be the best tool to communicate this information to stakeholders?

A.

Status report

B.

Issue log

C.

Risk report

D.

Risk register

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

A.

Quote

B.

Information

C.

Proposal

D.

Bid

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

A.

Cultural differences

B.

Technological factors

C.

Time zones

D.

Language barriers

The PMO wants to streamline the routing and approval of project activities to provide up-to-date visibility of the status. Which of the following collaboration tools would be most appropriate to use?

A.

Real-time, multi-authoring tool

B.

Wiki knowledge base and search engine

C.

Workflow and e-signature platform

D.

File-sharing platform and storage system

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

A.

Informal communication

B.

Formal communication

C.

Synchronous communication

D.

Asynchronous communication

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

A.

Smoke testing

B.

Regression testing

C.

Unit testing

D.

User acceptance testing

Which of the following would help a project manager identify that project goals have been reached?

A.

Audit report

B.

Key performance indicators

C.

Backlog

D.

Lessons learned

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary