Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Which of the following considers factors such as reliability, scalability, security, and cost-effectiveness within project goals and objectives?

A.

DevOps architecture

B.

Computing services

C.

Data warehouse

D.

Networking and connectivity

Given the following chart showing committed work (orange) vs. actual work completed (blue) across 10 sprints:

Which of the following best describes the team's performance?

A.

The team needs to adjust the planned work based on results.

B.

The team’s velocity is getting better.

C.

The team understands its velocity and is planning in an accurate manner.

D.

The team is doing more work than planned.

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

A.

Hold a new backlog prioritization meeting.

B.

Add milestones to check the project's progress.

C.

Adjust the task relationship to complete coding in advance.

D.

Apply contingency buffers to the critical path.

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

A.

Smoke testing

B.

Regression testing

C.

Unit testing

D.

User acceptance testing

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Which of the following provides the best justification for undertaking a project?

A.

Scope statement

B.

Business case

C.

Sponsor request

D.

Project charter

A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?

A.

Identify and assess stakeholders.

B.

Hold daily status meetings.

C.

Remove access and plan the project sign-off.

D.

Review assumptions and constraints for input to the risk register.

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

A.

The team is working in different rooms within the same building.

B.

The team is working remotely two days per week.

C.

The team has members distributed around the world in different time zones.

D.

The team is based in the same office but has a large number of members.

A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?

A.

Avoid

B.

Transfer

C.

Accept

D.

Share

Which of the following would be the most helpful in providing customers with an application accessible via a web browser?

A.

IaaS

B.

SaaS

C.

PaaS

D.

XaaS