Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?

A.

Meeting cadence

B.

Gap analysis

C.

Dashboard

D.

Adoption training

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?

A.

Pareto

B.

Scatter

C.

Network

D.

Fishbone

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

A.

Application deployment

B.

Rollback plans

C.

Validation checks

D.

Maintenance window schedules

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

A.

Transfer

B.

Mitigate

C.

Avoid

D.

Accept

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?

A.

Based on the rule of seven, the process is under control

B.

The amount of data is insufficient to determine if quality is low.

C.

The process is out of control and should be revised.

D.

The goal should be adjusted since most of the data points are close to the lower limit.