Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

A.

Add a new risk.

B.

Perform an impact analysis.

C.

Escalate to the sponsor.

D.

Raise a change request.

Which of the following offers administrators more direct control over operating systems?

A.

Infrastructure as a service

B.

Software as a service

C.

Functions as a service

D.

Platform as a service

A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?

A.

SWOT

B.

Risk register

C.

Project schedule

D.

RAC

Which of the following best explains the importance of artifacts during the discovery/concept preparation phase of a project?

A.

To develop a detailed project plan and timeline

B.

To enable a lessons learned session

C.

To identify and assess potential vendors for the project

D.

To ensure that all stakeholders have a shared understanding of the project's objectives

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

Which of the following was the initial cause of the issue?

A.

Inadequate memory

B.

Incorrect configuration

C.

Lack of infrastructure

D.

Inadequate instructions

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

A.

A negative correlation exists between the number of mistakes and the working hours.

B.

No correlation exists between the number of mistakes and the working hours.

C.

A low correlation exists between the working hours and the number of mistakes.

D.

A positive correlation exists between the number of mistakes and the working hours.

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.

A project manager is leading the implementation of a new service for a well-known, global company for which brand image is most important. The project will rely on contracted services. As part of the request for proposal process, the project team has identified a short list of vendors to submit proposals. Which of the following items should the project team consider as a primary factor to remove a vendor from consideration?

A.

The vendor's proposed schedule does not align with the desired schedule.

B.

The vendor is new and not well established in the market.

C.

The vendor has been linked to ESG concerns within the past month

D.

The vendor's quote was the highest of all the proposals.