Which of the following contract types presents the most risk for the buyer?

A.

Cost-plus percentage of cost

B.

Cost-plus-incentive fee

C.

Cost-plus-fixed-fee

D.

Firm fixed-price

A meeting agenda included the following items:

. Review the goals of the project.

. Review the progress of the project.

. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?

A.

Stand-up

B.

Monthly status

C.

Gap analysis

D.

Gate review

After new capabilities were deployed in a system, issues with preexisting capabilities were reported. Which of the following testing cycles should be used to prevent this issue?

A.

Performance testing

B.

User acceptance testing

C.

Stress testing

D.

Unit testing

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

A.

Resource allocation

B.

Communication security

C.

Technological factors

D.

Cultural differences

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

A.

Waterfall method

B.

Simulation method

C.

Precedence diagramming method

D.

Cost ratio analysis

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

A.

Issue log

B.

Gantt chart

C.

Milestone chart

D.

Change control log

A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?

A.

Issue, issue

B.

Issue, risk

C.

Risk, issue

D.

Risk, risk

A company plans to install new servers. The project manager receives a notification that the manufacturer may be in financial trouble, so the servers will be sourced from another vendor. Which of the following risk management strategies should the project manager use?

A.

Share

B.

Exploit

C.

Mitigate

D.

Avoid

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?

A.

Enterprise resource planning and end user applications

B.

Electronic document and record management systems

C.

Customer relationship management and databases

D.

Content management and financial systems