Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A retail store is rolling out a new point-of-sale solution to several locations where the staff members normally use cash registers. Which of the following activities will best assist staff members with integrating this new solution? (Select two).

A.

Documentation

B.

Team collaboration

C.

Gap analysis

D.

Training sessions

E.

Touch points

F.

Progress monitoring

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

A.

Mitigate

B.

Transfer

C.

Accept

D.

Share

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

A.

Update the risk register.

B.

Escalate the issue for exceptional approval.

C.

Communicate to the stakeholders.

D.

Submit a duplicate change request.

A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?

A.

Avoid injuries by using robots to perform tasks.

B.

Transfer risk to an insurance company.

C.

Mitigate risk by training the construction workers.

D.

Accept the risks inherent to construction.

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

A.

Build

B.

Subscription

C.

Lease

D.

Buy

A software development team completed the development and testing of a new accounting software system for a client. Which of the following should the team do next?

A.

User acceptance testing

B.

Unit testing

C.

Performance testing

D.

Audits and inspections

Which of the following is the focus of DevSecOps?

A.

Securing, testing, and maintaining new software

B.

Developing, testing, and maintaining software

C.

Developing, maintaining, and securing software

D.

Developing, securing, and testing software

Which of the following can a project manager infer from the following velocity chart?

A.

The project is on schedule.

B.

The project Is ahead of schedule.

C.

The project is behind schedule.

D.

The project is at risk.

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

A.

Memorandum of understanding

B.

Request for information

C.

Statement of work

D.

Non-disclosure agreement