A retail store is rolling out a new point-of-sale solution to several locations where the staff members normally use cash registers. Which of the following activities will best assist staff members with integrating this new solution? (Select two).
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?
A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?
A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?
A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?
A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?
A software development team completed the development and testing of a new accounting software system for a client. Which of the following should the team do next?
Which of the following is the focus of DevSecOps?
Which of the following can a project manager infer from the following velocity chart?
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?