A project team that handles sensitive data analysis recently onboarded three new employees. Which of the following should the PM do first?

A.

Check employee security clearance

B.

Allow access to the internet on corporate computers

C.

Train the new employees to handle sensitive data

D.

Execute an analysis of the sensitive data

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

A.

Project network diagram

B.

Fishbone diagram

C.

Burndown chart

D.

Milestone chart

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

A.

Project network diagram

B.

Gantt chart

C.

Issue log

D.

Risk report

A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?

A.

RFP

B.

RFQ

C.

RFB

D.

RFI

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

A.

Request a change control ticket.

B.

Review the schedule plan.

C.

Refine the project documentation.

D.

Revise the communication plan.

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

A.

Evaluating the project

B.

Releasing the resources

C.

Closing the contracts

D.

Reconciling the budget

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

A.

Transfer

B.

Mitigate

C.

Avoid

D.

Accept

Which of the following is the main reason for documenting artifacts?

A.

To provide a record of the project's progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

A software development team implemented an approved change but does not obtain the expected results. The team notifies the change control board (CCB) about the failed change. Which of the following control processes is being followed?

A.

Scope creep

B.

Recovery plan

C.

Incident report

D.

Risk response