Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?

A.

Social

B.

Regulatory

C.

Environmental

D.

Governmental

Which of the following tools is best to use for storing lessons learned?

A.

Whiteboard

B.

Wiki knowledge base

C.

Content management system

D.

Workflow platform

Which of the following can be inferred?

A.

The project will be completed on time.

B.

Task D must be reworked.

C.

Task B needs to be finished before task C starts.

D.

The project is over budget and behind schedule.

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report

Which of the following activities are performed during the closing phase? (Select three).

A.

Requesting project charter sign-off

B.

Recognizing project team efforts and rewarding team members

C.

Working with the financial team to obtain return of investment

D.

Revoking resource credentials from the system

E.

Updating the risk register with new findings

F.

Informing the functional manager about the release of resources

G.

Monitoring project team performance

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.