Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

A utility company issued a directive stating that projects impacting operating systems will not be executed during hurricane season. Which of the following is being acknowledged by this directive?

A.

Company brand value

B.

National environments

C.

Standard operating procedures

D.

Local emergency policies

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

A.

Memorandum of understanding

B.

Request for information

C.

Statement of work

D.

Non-disclosure agreement

A project manager must determine how ideas from the organization and results from the review committee should move through the enterprise for a new project. Which of the following does the project manager need to do?

A.

Establish communication channels

B.

Plan a kickoff meeting

C.

Develop a responsibility assignment matrix

D.

Identify the stakeholders

The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?

A.

Grant the client access to the project repository.

B.

Create a chat to communicate in real time.

C.

Schedule a weekly status meeting.

D.

Send a weekly status report by email.

A new stakeholder has joined a project and has a different vision of the scope. The sponsor is requiring the project manager to provide a document in which the initial scope of the project is defined. Which of the following should the project manager do next to clarify the differences?

A.

Create a new project management plan.

B.

Collect all project meeting minutes.

C.

Perform project scope management.

D.

Review the project charter.

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Which of the following would help a project manager identify that project goals have been reached?

A.

Audit report

B.

Key performance indicators

C.

Backlog

D.

Lessons learned

Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).

A.

Real-time surveys/polling

B.

Wiki knowledge base

C.

Spreadsheets

D.

Meetings/face-to-face

E.

Real-time, multiauthoring editing software

F.

Charting/diagramming