A ________ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

A.

Parametric

B.

Bottom up.

C.

Budget

D.

Top down.

E.

Definitive.

Which of the following is an input to Develop Human Resource Plan?

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

When can pre-assignment of project team members occur?

A.

When the project uses capital expenditures.

B.

When the required staff can be acquired from outside sources.

C.

When the project would be ignored due to travel expenses.

D.

When the project is the result of specific people being promised as part of a competitive proposal.

In which of the following is the cost of risk hidden by the contractor?

A.

Fixed Price Plus Incentive

B.

Firm Fixed Price Contract and Fixed Price Plus Incentive

C.

Firm Fixed Price Contract

D.

Cost Plus Percentage of Cost

E.

Cost Plus Fixed Price

When would resource leveling be applied to a schedule model?

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Information distribution involves making needed information available to project stakeholders in a timely manner.

What is an output from information distribution?

A.

Earned value analysis

B.

Trend analysis

C.

Project records

D.

Performance reviews

The person in the organization that authorizes the commencement of a project is the ______________?

A.

Project Admin

B.

Sponsor

C.

Project Manager

D.

Senior Manager