The Communications Management Plan should contain the following:
A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a _____ manager.
Which of the following is an input to Collect Requirements?
The project charter:
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?
An Ishikawa or fishbone diagram is used for which of the following?
Project contracts generally fall into which of the following three broad categories?
The project manager and project sponsor are discussing the project costs and whether it is better to have their own company do part of the project or hire another company to do the work. If they asked for your opinion, you might say it would be better to do the work yourself if:
A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed.
Which activities have float available?
You have assembled your thoughts into a message. As you pass this information to a second party, you are giving this person you’re:
The critical path in a schedule network is the path that:
You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of scope definition.
Which of the following could happen if you don't correct this?
Which of the following is an example of the simplest fixed-price contract?
The Project Management Body of Knowledge (PMBOK Guide) should be considered as a:
A computer tape which contains historical project information is called ____ tape.