Executive stakeholders require both current metric reports and a weekly recap on a project.
How can both needs be met?
A.
Create a program-specific dashboard for the metrics and set up a weekly automated report to send.
B.
Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.
C.
Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.
The Answer Is:
A
Want to know why?
Explanation:
In Workfront, creating a program-specific dashboard allows for the presentation of real-time data to stakeholders. Additionally, automated reports can be set to send out weekly, meeting the requirement for a consistent recap. This automation reduces the manual effort of downloading and sending reports each week.