Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Which two statements are true about Groups and Teams? (Choose two.)

A.

A Team can be assigned to a task, but a Group cannot be assigned to a task.

B.

Objects can be shared with either a Group or a Team.

C.

A Group can be assigned to a task, but a Team cannot be assigned to a task.

D.

Work requests can be routed to either a Group or a Team.

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

A.

Start No Later Than

B.

Must Start On

C.

As Late As Possible

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?

A.

Change the Task Duration Type to Effort Driven

B.

Change the Task Duration Type to Calculated Work

C.

Change the Task Constraint to Fixed Dates

D.

Change the Task Constraint to As Soon As Possible

The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.

Which task settings need to be configured to meet these requirements?

A.

The Task Constraint should be set to Must Start On with Planned Time set to 2 weeks and Duration set to 10 hours.

B.

The Task Constraint should be set to Must Start On with Planned Hours set to 10 hours and Duration set to 2 weeks.

C.

The Task Constraint should be set to Start Date of September 23 with Planned Hours set to 10 hours and Issue Duration set to 2 weeks.

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

A.

Utilization section

B.

Hours tab

C.

Finance section

Given this information regarding a Task:

    Planned Start Date: May 14

    Actual Start Date: May 14

    Planned Completion Date: May 20

    Projected Completion Date: May 22

    Percent Complete: 50%

    Duration: 5 Days

    Planned Hours: 8 Hours

    Status: In ProgressIf today's date were May 19, what would be the Task's progress status?

A.

Behind

B.

On Time

C.

At Risk

A copywriter wants to see his incomplete tasks for projects to which he is assigned.

Which steps should the project manager take to create a custom Workfront report with this information?

A.

Visit the Reports page, create a new Project report, add filters for Project Status > Equal > Current and Project Owner ID > Equal > [User Name]

B.

Visit the Reports page, create a new Task report, and add the filter Task > Assigned To Role ID > Equal > Copywriter and Task Status > Not Equal > Complete

C.

Visit the Reports page, create a new Task report, add filters for Task Status > Not Equal > Complete and Assignment Users Name > Equal > [User Name]

How is the primary assignee of a task determined?

A.

By the user on a task that has a primary job role.

B.

By the Home Team assigned to a task.

C.

By the user that is assigned first to a task.

A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.

How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

A.

Share the program with Program Manager A with Manage access and ensure the system administrator adjusts Program Manager A's access level.

B.

Share the program with Program Manager A with Manage access and ensure Program Manager A understands they cannot manage the rest of the portfolio.

C.

Share the program with Program Manager A with Manage access and remove Program Manager A's Manage access on the portfolio.

Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?

A.

Update the project status.

B.

Recalculate the project timeline.

C.

Update the project baseline.