The Economic Case in the FBC has been completed and the Senior Responsible Owner, has asked that assurance of the
investment decision be held for the project before the benefits realization plans are produced.
Should assurance of the investment decision be held at this point?
Which 2 attributes demonstrate that this option supports the key CSF Potential achievability?
Using the Scenario, answer the following questions.
Column 1 is a list of areas of interest to be included in the communications planned for the Pittville project. For each area of interest
in Column 1, select from Column 2 the MOST appropriate stakeholder group to which it will apply. Each selection from Column 2
can be used once, more than once or not at all.
Which 2 observations correctly evaluate the affordability of the Pittville project?
Using the Scenario, answer the following questions about roles and responsibilities on the Pittville project.
Which action should be completed by the sponsor for the Western Area Learning Improvements Programme?
The Local Education Authority Director has been appointed as the Senior Responsible Owner for the Western Area Learning Improvement Programme.
Which action is MOST appropriate for this role?
Using the Scenario, answer the following questions about the Management Case section of the Full Business Case for
the Pittville project.
Decide whether the entry is appropriate for the document identified and select the responses that support your decision.
Remember to select 2 answers to each question.
The Programme and Project Management Framework section states:
1. The Programme Director is to be responsible for the Western Area Learning Improvements Programme.
2. Project progress reports are to be provided to the Consortium at the end of each month.
Which 2 statements apply to these entries?
Using the Scenario and the information below, answer the following questions about the creation
of the short listed options for the Pittville project.
Spending Objectives
At least 15% increase in rate of participation
A 15% increase in attainment of qualification
At least 65 education courses
Critical Success Factors
Strategic fit and business needs - fit for purpose schools and universities attractive to 16-18-year-old
learners
Potential Value For Money
Supply side capacity and capability
Potential affordability
Potential achievability
Remember to select 2 answers to each question.
Scoping Solution 1: 'Current level of participation, 55 education courses and current qualification
success rate'
Which 2 statements are correct about this entry in the Options Framework?
The new campus scheme will take three years to complete. Projected inflation over this period will mean that staffing costs will be 6%
higher when the campus is operational.
Should this increase be managed as a risk to the project?
Which detail should be explained in the Commercial Case?