You are currently leading a major ongoing change initiative. You observe that the project lacks support, lacks active engagement in the change effort and loses interest in the change effort. Under the circumstances, what would be the best strategy to address this constraint and enable an intervention to happen?

A.

The risk management and intervention strategy

B.

The change strategy

C.

The stakeholder strategy

D.

The communication strategy

What is the most significant indicator of an effective communications plan?

A.

The feedback channels provide impacted employees the opportunity to engage

B.

The communications strategy is clear and contains key messages and responsibilities

C.

Stakeholders are able to build awareness, establish understanding and define core ownership around delivery of messages

D.

Subject matter experts are engaged to give guidance in the delivery of the communication

Who conducts the lessons learned evaluation?

A.

The primary sponsor and project manager excluding the change management lead

B.

The change management lead along with the project manager when possible

C.

The primary sponsor and members of the executive board

D.

All members of the change management team including the sponsor

What is the purpose of completing the case for change?

A.

Identify deliverables and activities associated with the change

B.

Identify reasons and benefits associated with the change

C.

Identify methodology and framework to be applied to implement the change

D.

Understand effort and resources required to implement the change

You are the communication change lead developing the communications strategy for a new change initiative. What would you choose as an input when you plan your communications strategy?

A.

Change impact assessment

B.

Budget assessment

C.

Resource assessment

D.

Risk assessment

Which change management topics should the change manager review during sponsor coaching?

A.

Lessons learned from previous projects

B.

Common project manager mistakes

C.

Role, responsibilities and actions to visibly support the change

D.

Requests for additional funding for change management activities

What are three main components you should include in a communications plan?

A.

Frequency of communication, RACI and communication strategy

B.

Target audience, key messages and desired outcomes

C.

Cost and resourcing, measures of success and monitoring feedback

D.

Communication channels, stakeholder analysis and learning and development plan

How would you ensure a competency for managing change exists in your organization?

A.

Identify positive outcomes from each change project and opportunities for improvement

B.

Assess change readiness in the organization in an ongoing fashion

C.

Define a process to determine sponsorship effectiveness

D.

Identify clarity around change goals and outcomes achieved

What element included in a stakeholder engagement plan ensures that the plan meets the intended outcomes?

A.

Clear metrics

B.

Stakeholder analysis

C.

Tools

D.

Informal communication

A service company conducted a change management project to increase customer satisfaction for one year. What can be done to sustain the positive trend on customer satisfaction observed during the project?

A.

Design and conduct a lessons learned evaluation at the end of the project and share improvements for future change programs

B.

Change objectives and goals focused on improving customer satisfaction

C.

Revise the current vision statement to include a focus on customer satisfaction

D.

Change current communications channels, tools and methods to focus on customer satisfaction