Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

A.

Use gross building square footages. The pluses and minuses all average out.

B.

Look at each activity independently and don't follow specific logic paths when assigning activity durations.

C.

Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

D.

Use the people responsible for performing the work as a resource to assign activity durations.

Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

A.

Drafting and Proofing the Manual.

B.

Packaging only.

C.

Printing the Manual.

D.

Testing, Manufacturing and Packaging.

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

A.

Project objectives in terms of cost, schedule and quality measures

B.

Project contract between the contractor and owner

C.

Project justification

D.

Project deliverables

Is activity 7001 pictured correctly in the precedence diagram?

A.

No, the total float is not shown correctly.

B.

Yes, except the early finish date is not shown.

C.

No, the start-to-start and finish-to-finish relationships are backwards.

D.

Yes, the duration is 48 days.

Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

A.

3.3%

B.

2.2%

C.

23%

D.

2 4%

What changes to logic would eliminate Activity B from the critical path?

A.

Replace the relationship from Activity B to Activity C with SSO

B.

Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0

C.

Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO

D.

Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C

You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor has included codes for each activity that identify {1) the category of work and (2) the trade/subcontract performing the work. What can this code information be used for?

A.

Group schedule activities together based on their start dates

B.

Display detailed information regarding the sequencing of activities in the schedule

C.

Organize reports to group related work activities

D.

Display resources me contractor plans to use on each activity

For which of these delays should an owner grant a time extension?

A.

Structural steel shop drawings.

B.

Shop drawings and centrifuge delay.

C.

Differing site conditions at parking structure.

D.

Differing site conditions and centrifuge delay.

The EBS is established by:

A.

The contractor s planning and scheduling office

B.

The government entity with the authority to approve/stop the work

C.

The entity with the authority to fund and direct the enterprise

D.

The contractors and subcontractors

Determine the correct formula and date for the late finish for Activity 6002.

A.

LS of 6003 plus 1 day equaling 09 Mar 2023

B.

LS of 6003 less 1 day equaling 09 Mar 2022

C.

LS of 6003 less 1 day equaling 09 Mar 2023

D.

LS of 6003 plus 1 day equaling 09 Mar 2022