By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

A.

Acceleration.

B.

Production output.

C.

Productivity loss.

D.

Productivity efficiency.

What method offers the best chance of the schedule being used effectively to implement the project in the field?

A.

Issue detailed schedule updates as frequently as possible.

B.

Obtain consent and agreement to the schedule from the key project personnel.

C.

Include detailed and stringent set of scheduling specifications in the contract.

D.

Allow large time contingencies on milestones and completion deadlines.

The linear scheduling velocity diagram has the following two-axis:

A.

Location and crew size

B.

Time and location

C.

Time and rate of progress

D.

Time and crew size

Determine the correct formula and date for the late finish for Activity 6002.

A.

LS of 6003 plus 1 day equaling 09 Mar 2023

B.

LS of 6003 less 1 day equaling 09 Mar 2022

C.

LS of 6003 less 1 day equaling 09 Mar 2023

D.

LS of 6003 plus 1 day equaling 09 Mar 2022

Which of the following phases does NOT describe the commonly accepted construction life cycle?

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.

Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

A.

$271,000

B.

$299,000

C.

$139,000

D.

$289,000

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

A.

Not suitable for complicated projects with multiple planned critical paths.

B.

Accuracy is increased by inserting delaying events into the as-planned schedule.

C.

Not suitable for projects with long durations.

D.

Less accurate as the analysis advances through the project.

If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

A.

0 calendar days.

B.

-14 calendar days.

C.

-20 calendar days.

D.

10 calendar days.

Why does activity 1001 have two successor activities?

A.

Because the late finish of 1001 and the late start of 7001 require two successors

B.

Because the problem could not effectively work with only one successor

C.

Because there are two defined logic paths for the work

D.

Because the duration of activities 2001, 2002 and 200.f require two successors

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

A.

Finish-no-earlier constraint on the first activity

B.

Finish-no-earlier constraint on the last activity

C.

Finish-no-later constraint on the last activity

D.

Start-no-later constraint on the first activity