Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

An earned value-based project control system can use either of which two budgets as the basis of its calculations?
Determine the correct formula and date for the late finish for Activity 9004.
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

If all other work proceeds according to the Baseline plan, how many times will the critical path change?

Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
When a fragnet of activities represents a known schedule risk, which activity will most likely change the overall outcome?
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?
Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor's baseline schedule submittal includes a bar chart, but no CPM diagram. Which of the following is the most significant shortcoming to using a bar chart to review the baseline?