Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

Determine the correct formula and date for the late finish for Activity 2002.

A.

LS.2003 - 1 day -> 11.06.01.

B.

LS.2003 - 1 day -> 10-06-01.

C.

LS.2003 + 1 day -> 10-07-01.

D.

LS.2003 - 1 day -> 10-05-01.

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

A.

Negative float.

B.

Free float.

C.

Total float.

D.

Interfering float.

What is the result of a forward pass calculation?

A.

Value of total float for individual activities

B.

Early start and early finish date for individual activities

C.

Value of free float for individual activities

D.

Critical path

Resource planning must take all of the following into account except for:

A.

Types of materials, equipment and labor skills required to complete the project.

B.

Earned value techniques established for the project.

C.

Time available to complete the project.

D.

Cash flow (expenditure) limitations for completing work on the project.

What is a key first step in developing a critical path method schedule?

A.

Drawing a bar chart of the key phrases of the work.

B.

Defining the execution plan to meet the required scope of work.

C.

Setting out the resource to be used and its limitations.

D.

Drawing the logic diagram.

In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?

A.

4001, 5001, and 6001

B.

2003 and 7001

C.

4001 and 5001

D.

2004, 4001. and 5001

What is the cycle time?

A.

5 minutes

B.

17 minutes

C.

14 minutes

D.

6 minutes

Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

A.

91 days

B.

183 days

C.

193 days

D.

168 days

What is the relationship depicted between Activity G and Activity H?

A.

You cannot tell with the supplied information.

B.

Start-to-start.

C.

Finish-to-start.

D.

Finish-to-finish.

Estimate to complete (ETC) is __________________.

A.

The expected remaining cost needed to complete an activity, group of activities or the project

B.

The costs actually incurred in accomplishing the work performed

C.

The expected total cost of an activity, group of activities or the project

D.

The value of the completed work expressed in terms of the budget assigned to that work