Cyber Monday Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Each of the following accurately describes total float in a schedule EXCEPT:

A.

The amount of time an activity can be delayed without delaying the overall project completion time.

B.

Can be positive or negative.

C.

The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.

D.

Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

The addition of which of the following relationships would cause a logic loop?

A.

O H - D

B.

O C - J

C.

O F-I

D.

O l-C

Based on the available scope information and required accuracy, different cost estimated models or methodologies are utilized Which of the following statements is NOT true?

A.

The Deterministic model is used when Class 3 through 1 estimates are required

B.

The Parametric model is used when Class 5 or Class 4 estimates are required

C.

The Deterministic model is used when Class 5 through 3 estimated are required

D.

The Parametric model is used when detailed quantities are not known

Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

A.

91 days

B.

183 days

C.

145 days

D.

53 days

The project goals_________.

A.

are the foundation for breakdown structures

B.

are defined independent of any external stakeholder opinions

C.

quantify performance and interface requirements

D.

consider all aspects of the project

When project risk is reflected in scheduled activities, what is the most significant characteristic of those activities?

A.

The level of resources available to the activity

B.

The Remaining Duration of the activity

C.

The criticality of toe activities

D.

The Late Start of the last activity in that float path

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

A.

Not suitable for complicated projects with multiple planned critical paths.

B.

Accuracy is increased by inserting delaying events into the as-planned schedule.

C.

Not suitable for projects with long durations.

D.

Less accurate as the analysis advances through the project.

The project team must communicate the project plan, goals and objectives to all stakeholders to ensure the stakeholders understand the plan, goals and objectives and then continue this communication throughout the project life Which statement below would stakeholders NOT be expected to contribute?

A.

Stakeholders review the basis the schedule after the schedule is developed

B.

Stakeholder communication should be the single most Important objective of a program of key cost and schedule performance indicators (KPls)

C.

Early in the planning process, a set of well-defined goals and objectives is reviewed by the stakeholders

D.

The key to successful acceptance by all stakeholders is a set of well-defined goals and objectives which should be Identified early in the planning process

Why does activity 11001 not show successor activities?

A.

The early finish and late finish are circular

B.

It is the penultimate work required for the project

C.

The scheduler forgot to add the successor activities

D.

It is the final activity for the required work for the project

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

A.

The project plans and specifications

B.

The project geotechnical report

C.

The regulations published by the government aviation agency

D.

The government's report on future high-clearance bridge projects