Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

A.

02-19-04

B.

03-21-04

C.

03-11-04

D.

03-20-04

What is the free float for Activity F?

A.

3 months.

B.

0months.

C.

1months.

D.

2month.

As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

A.

A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001

B.

A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity 6002.

C.

A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag

D.

A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002

What does the heavy, vertical line at "X" represent?

A.

Delay fault line.

B.

The status or data date.

C.

Change-over limits.

D.

International Date Line.

Which of the following is NOT true?

A.

Remaining durations can exceed original durations.

B.

Constraints can interfere with the longest path calculation.

C.

Multiple calendars can affect the total float calculation.

D.

A network must contain only one Critical Path.

What was the original planned duration for Activity A through Activity G?

A.

26.

B.

28.

C.

24.

D.

25.

The activity with the most total float is:

A.

Activity I.

B.

Activity C.

C.

Activity F.

D.

Activity D.

Project delays are best analyzed

A.

After either the contractor or the owner acknowledges ^responsibility for the delay.

B.

Contemporaneously with the delay.

C.

By an expert after the project is finished when complete records are available and the impact is known.

D.

Late in the project.

If all other work proceeds according to the Baseline plan, how many times will the critical path change?

A.

2.

B.

1.

C.

Does not change.

D.

3.

During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

A.

Delay product release by 5 days.

B.

Expedite packaging by 5 days.

C.

Expedite printing by 5 days.

D.

Delay manufacturing by 5 days.