What day would Activity C complete if the duration of Activity A was reduced by five days?

A.

35

B.

30

C.

45

D.

40

The work breakdown structure is used to organize

A.

"Smart activity ID codes" representing similar items of scheduled work

B.

The chart of accounts

C.

Similar activity coding of schedule activities

D.

The smallest defined work packet

As the project plan is developed a mechanism is developed to communicate the projects organic structures that will facilitate reporting against the baseline schedule and cost estimate or budget Which of the following is NOT used for reporting?

A.

The Resource Breakdown Structure (RBS)

B.

The Work Breakdown Structure (WBS)

C.

The Organization Breakdown Structure (OBS)

D.

The Cost Breakdown Structure (CBS)

If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

A.

8 days

B.

6 days

C.

4 days

D.

5 days

NO: 98

The activity with the most total float is:

A.

Activity I.

B.

Activity C.

C.

Activity F.

D.

Activity D.

At the end of month one, did the delay to the parking structure foundation delay the project?

A.

NO.

B.

Yes, by 4 calendar days.

C.

Yes, by 14 calendar days.

D.

Yes, by 9 calendar days.

SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?

A.

SUBCO direct labor and equipment rates

B.

BILCO liquidated damages in the SDOT contract

C.

Pending negotiations with GOUGE.

D.

The distance of SUBCO to your project

Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

A.

C.

B.

B.

C.

S.

D.

W.

A good change management plan___________.

A.

is provided to stakeholders after it is created

B.

is detailed during the planning phase

C.

tracks minor decisions

D.

involves only the project controls team

Schedules are periodically updated to reflect progress. What step should NOT occur before the update is considered complete?

A.

All managers should be encouraged to review contiguous activity status

B.

The process of each activity should be indicated by the responsible manager

C.

The critical path should not be revisited to ensure all the downstream logic and durations are still accurate

D.

The project team should be asked to review status for accuracy