What day would Activity C complete if the duration of Activity A was reduced by five days?
The work breakdown structure is used to organize
As the project plan is developed a mechanism is developed to communicate the projects organic structures that will facilitate reporting against the baseline schedule and cost estimate or budget Which of the following is NOT used for reporting?
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
NO: 98
The activity with the most total float is:

At the end of month one, did the delay to the parking structure foundation delay the project?
SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
A good change management plan___________.
Schedules are periodically updated to reflect progress. What step should NOT occur before the update is considered complete?