Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

What method offers the best chance of the schedule being used effectively to implement the project in the field?

A.

Issue detailed schedule updates as frequently as possible.

B.

Obtain consent and agreement to the schedule from the key project personnel.

C.

Include detailed and stringent set of scheduling specifications in the contract.

D.

Allow large time contingencies on milestones and completion deadlines.

Which of the following procedures is generally recognized as acceptable when updating a schedule?

A.

Report an actual date when the activity is on a non-work calendar for that date

B.

Change a previously reported actual date

C.

Change the WBS assignment for an activity

D.

Change a calculated date in the future

What is the relationship depicted between Activity G and Activity H?

A.

You cannot tell with the supplied information.

B.

Start-to-start.

C.

Finish-to-start.

D.

Finish-to-finish.

What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

A.

Use the progressed portion of the critical path of all the updates previous to the current update.

B.

Use the progressed portion of the critical path of the baseline schedule.

C.

Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.

D.

Use the forward-looking critical path of the most current updates.

During the Bid Phase, do the planning and scheduling project documents impact the Bid pricing?

A.

The bid does not reflect details of planning and scheduling

B.

The bid should reflect the level of planning and scheduling noted on similar projects with this client

C.

The bid should reflect the project plan incorporating all planning and scheduling elements

D.

The bid should incorporate input from the manager responsible for planning and scheduling if the bid is successful

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?

A.

The duration for drywall installation should De proportional to how critical the activity is

B.

Review the drywall quantity, methods and location with the project superintendent to determine a reasonable duration

C.

Review the location of drywall work in the contract drawings

D.

Divide the quantity of drywall by the construction crew's dairy production rate for this work

Determine the correct formula and date for the late start for the Activity 11001:

A.

LF of 11001 less 27 days plus 1 day equaling 14 Jan 2024

B.

LF of 1000 less 25 days equaling 16 Jan 2024

C.

LF of 11001 less duration of 11001 equaling 16 Jan 2024

D.

LF of 11001 less 25 days plus 1 day equaling 16 Jan 2024

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor has included several reports with its submittal, including a report that sorts all activities by total float. What is the value of this report?

A.

Allows you to review activities in the order they could start

B.

Allows you to confirm the current logical flow of the work

C.

Allows you to determine which activities will take the longest

D.

Allows you to determine which activities will be performed by the owner

What defines a KPI?

A.

Phase milestones

B.

Initiation of a weather risk window

C.

Key discrete project final or interim goals

D.

Interim milestones related to weather phasing

Which of the following phases does NOT describe the commonly accepted construction life cycle?

A.

Claims and disputes phase.

B.

Installation phase.

C.

Planning and design phase.

D.

Turnover and start-up phase.