Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Which of the following best describes the concept of total cost management:

A.

A method of quantifying construction damages where the total job costs are subtracted from the original bid or estimate to determine the total cost amount for a claim

B.

The practices and processes utilized to manage the total life cycle cost investment in a portfolio of strategic assets

C.

A job cost system for ensuring all aspects of a particular manufacturing process are accumulated completely

D.

An integrating process that maps the fields of practice of cost engineering without linking it to project management, resource management, or accounting

refers to the process of calculating and reporting the non-monetary functions of the strategic asset portfolio.

A.

Asset performance assessment

B.

Asset project reporting

C.

Asset investment decision and funding

D.

Asset performance measurement

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The following question requires your selection of Scenario 1.4.15Q from the right side of your split screen. using the drop down menu, to reference during your response/choice of responses

What is the amount of capital recovery with salvage?

A.

$11,499.00

B.

$4,124.00

C.

$9,876.00

D.

$10,765.00

The purpose of a communication must be understood by ____________ if the message is to be clear to the

A.

Workers; management

B.

The speaker; the receiver

C.

Management; workers

D.

The receiver; the speaker

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?

A.

Recalculate the early finish for each activity

B.

Recalculate the early start for each activity

C.

Update the remaining duration for each activity

D.

Recalculate the critical path

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26(2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected:

A.

To be exactly the percentages stated

B.

To fall within the percentage range stated

C.

To be higher or lower that the percentages stated

D.

To be outside the percentages stated

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Given a unit price contract between the owner and contractor, each assumes the following:

A.

Bid unit rate, owner quantities can exceed estimate range Contractor can perform above

B.

Bid unit rate, owner quantities are within estimate range

C.

Contractor can perform at or below bid unit rate, owner quantities can exceed estimate range

D.

Contractor can perform at or below bid unit rate, owner quantities are within estimate range

You are reporting the following Earned Value Analysis information for the project:

EV= $1,500,000

AC=$1.000,000

PV= $2,000,000

What is the status of the project?

A.

Project is ahead of schedule, but over budget

B.

Project is behind schedule, but over budget

C.

Project is behind schedule, but under budget

D.

Project is ahead of schedule, but under budget

Which of the following is NOT an aspect of quality management?

A.

Quality assurance

B.

Quality planning

C.

Quality checking

D.

Quality control

Which of the lol owing comparisons is commonly used in forensics schedule analysis (FSA)?

A.

Cost performance index (CPI) to schedule performance index (SPI)

B.

Forensic productivity analysis

C.

Earned value vs scheduled value

D.

As-planned vs as-built