Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits

A.

Criteria A = OK, criteria B = OK, criteria C = OK

B.

Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK

C.

Criteria A = OK, criteria B = NOT OK, criteria C = NOT OK

D.

Criteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK

Which of the following phases in the fundamental test process is considered to deliver a document which can be used as a major input for test process improvement? 1 credit

A.

Test planning and control

B.

Test implementation & execution

C.

Evaluating exit criteria and reporting

D.

Test project closure

During test process improvement it is recommended to use standards where possible. Standards originate from various sources and they cover different subjects in relation to testing Pick TWO sources of software standards, useful to software testing from the ones mentioned below. 1 credit

A.

ISO 9126-1 ‘Software engineering- Product quality Part 1:

Quality model’ is an international standard, that provides a basis on which to define quality assurance solutions.

B.

ISA 4126-1 ‘Software engineering- Product quality Part 1:

Quality model’ is an international standard, that provides a basis on which to define quality assurance solutions.

C.

BS-7925-2 ‘Software testing. Software component testing is a national standard used internationally. It covers a number of testing techniques that may be useful both on component testing level and on system testing level.

D.

SY-395-01 ‘Standard for East Coast Hospital software’ is a regional standard adapted from a national one. Besides hospital software, this standard ought to be used also by other types of software system in the region.

E.

IEEE 829 ‘standard for software test documentation’ is an international standard to be following mandatory by all testing origination regardless of lifecycle models.

Which THREE activities would be valid steps during the development of the test strategy?2 credits (2 out of 3 correct 1 credit)

A.

Identify test staff members that will be involved in the system test

B.

Define test career paths

C.

Understand the software development life cycle used by the software house

D.

Assess the testing that needs to be done to minimize the risks

E.

Issue the test strategy document for review

F.

Define a master test plan template

G.

Perform a project risk analysis

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

a. Any deviation from the procedures described in the test strategy document

b. The overall estimated costs, timescales and resource requirements

c. A detailed schedule of testing activities

d. The development deliverables to be tested

e. Which test staff members (names) will be involved and when

f. Level of requirements coverage achieved

Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit

A.

a

B.

b

C.

c

D.

d

E.

e

F.

f

Which of the following would you least expect to form part of the analysis of initial tool costs? 1 credit

A.

Integration with other tools

B.

Learning time required to use the new tool

C.

Tool portability

D.

Evaluation of suitable tools

Select THREE issues from the options provided that should at least be raised. 1 credit

A.

Has there been sufficient comparison of tools?

B.

What are the problems we are trying to address?

C.

Do we have a set of tool requirements to validate the tool against?

D.

How will the implementation be organized?

E.

Which project will be selected to perform the tool pilot?

F.

Is customized training available?

G.

How will the change process be managed?

You have investigated different possibilities and selected four of them to present to IT management. Which of the proposals will you most likely give your highest recommendations? 3 credits

A.

Insourcing of test automation based on an offer from a local company ABC that has people who are specialists in system level capture-replay automation tools and they also do regular training courses in test automation methods and tools. They can then work closely with Vicki.

B.

Outsourcing of test automation based on an offer from an Asian company, AsiaAutoTest, which has people who are specialists in system level capture-replay automation tools. They also offer training and besides they offer to run and maintain the regression tests in the future.

C.

Internal offer from the development department of XYZ to create the regression package using CppUnit as test automation tool. One of the development groups have very good experiences in automating unit tests, and they are willing to do training as well.

D.

Solution from a tool vendor offering to educate two test team members in the use of their easy-to-use test automation capture replay tool over the first 3 month and based on that build the regression test suite. In addition to Vicki, Steve is the only one that has time available to be educated.

Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing? 1 credit

A.

Test environment more complex

B.

Define expectation for tasks and deliverables

C.

Clear channels of communications

D.

Possibly different cultures

E.

Testing of non-functional requirements

F.

Audit trail from requirements to test cases

G.

Applying test automation

What is the Risk Priority Number for risk item number 2? 2 credits

A.

16

B.

2

C.

1

D.

63