What issue must be present on the project site to achieve Location and Transportation Credit, High-Priority Site, Option 3. Brownfield Remediation?
A project's massing and site orientation can have a direct impact on which of the following prerequisites?
Short-term bicycle storage in Location and Transportation Credit, Bicycle Facilities must be within 100 ft. (30 m) walking distance of any:
While working on a 12,000 ft² (1,114.8 m²) medical building, a LEED AP asks the flooring manufacturer to submit the Environmental Product Declaration (EPD) for the flooring specified. The manufacturer doesn't have an EPD for their products, but all products meet ISO 14040/44 for Life Cycle Assessment (LCA). They ask if it would be acceptable to send the ISO 14040/44 LCA information in lieu of an EPD. How do you respond?
What building classification requires the energy model to determine the predicted power usage effectiveness (PUE) for Energy and Atmosphere Prerequisite, Minimum Energy Performance?
The owner of a large multi-building property is seeking LEED certification. In determining the LEED project boundaries the LEED AP may include non-contiguous parcels of land if
A project team has installed a rainwater harvesting system on site. In which of the following could this system be recognized?
What credit rewards customers who change their normal consumption patterns in response to the varying price of energy over time?
Energy and Atmosphere Credit, Demand Response
Energy and Atmosphere Credit, Advanced Energy Metering
Energy and Atmosphere Credit, Building Level Energy Metering
A project attempting to meet the preferred parking requirements for Location and Transportation Credit, Green Vehicles may provide what incentive to meet the requirements and highlight the project sustainable vehicle strategy?
Which item is included in the reuse calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction?