What percentage of a building's surface area may be excluded from the calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 2. Renovation of Abandoned or Blighted Buildings because of deterioration or damage when maintaining existing building structure, enclosure and interior structural elements?

A.

5%

B.

10%

C.

25%

D.

50%

A Healthcare Project is constructing a new building adjacent to an existing LEED Certified hospital facility. The new building's location is on the same hospital campus as the certified facility. The entire hospital campus was analyzed with an Environmental Site Assessment (ESA) as part of the certified facility's project scope. The new building project needs to complete a new Phase I ESA if

A.

the Phase II ESA uncovers suspected contamination

B.

contamination was identified by the certified facility

C.

the certified facility's Phase I ESA is older than 180 days

D.

the local equivalent standard is more stringent than ASTM E1527-05

According to ASHRAE 90.1-2019, small commercial buildings under 25,000 ft² (2,323 m²) require energy monitoring:

A.

At 15-minute intervals for total project electricity use

B.

At least monthly for submetered end-use electricity

C.

At least monthly for whole-building energy use for each energy source

A LEED Building Design and Construction: New Construction office building's HVAC system includes hot water from a central utility plant. The central utility plant is owned and operated by a management company. The office pays a flat fee for hot water, included as part of the lease. The management company does not meter or invoice for actual hot water consumption. For the project to meet the requirements for Energy and Atmosphere Prerequisite, Building-Level

Energy Metering, an energy meter must be installed for

A.

natural gas

B.

hot water at the main service point

C.

nothing, because the flat fee is included as part of the lease

D.

nothing, because the energy source is outside of the project's scope

When should a preliminary water budget analysis be conducted?

A.

At the time the design development is completed

B.

At the time the plumbing contractor is selected

C.

After completion of schematic design

D.

Before completion of schematic design

How is the distance between the project site and the manufacturing location determined for Materials and Resources Credit. Building Disclosure and Optimization - Sourcing of Raw Materials. Option 2. Leadership Extraction Practices?

A.

Roadway distance

B.

Straight line distance

C.

Rail freight distance

D.

Air freight distance

Several Materials and Resources credits give a bonus location valuation factor, which allows products extracted,

manufactured and produced within 100 mi. (161 km) of the project to take double valuation in credit calculations. The

intent of this bonus is

A.

to shorten construction duration by reducing shipping times

B.

to avoid spreading products with potentially invasive non-native pests

C.

to incentivize the purchase of products that support the local economy

D.

to promote design with indigenous materials in order to maintain local aesthetic quality

An owner has requested that the project team redesign a large office building. As part of the redesign, the owner would like to move the main entrance to the opposite side of the building. Achievement of which credit may be affected by the move?

A.

Location and Transportation Credit, High-Priority Site

B.

Location and Transportation Credit, Sensitive Land Protection

C.

Location and Transportation Credit, Surrounding Density and Diverse Uses

D.

Location and Transportation Credit, LEED for Neighborhood Development Location

Which of the following groups of documents is most likely to support both Indoor Environmental Quality Credit,

Thermal Comfort, and Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control?

A.

Architectural floor plans, mechanical plans, lighting plans

B.

Photometric plans, mechanical schedules, lamp specifications

C.

Lighting plans, surveys of occupants, sequence of operations

D.

Surveys of occupants, photometric plans, mechanical schedules

A luxury hotel project is in the design phase and is located on a scenic waterfront. It is one point away from attaining LEED Platinum certification. The LEED AP is recommending that the team pursue Innovation Credit, Innovation, Option 3. Additional Strategies. Which of the following credits would be desirable considering the location of the project?

A.

Energy and Atmosphere Credit, Optimize Energy Performance, Exemplary Performance

B.

Indoor Environmental Quality Credit, Quality Views, Exemplary Performance

C.

Indoor Environmental Quality Credit, Acoustic Performance, Exemplary Performance

D.

Energy and Atmosphere Credit, Enhanced Commissioning, Exemplary Performance