According to the Integrative Process Credit, Integrative Process, the goal-setting workshop should identify

A.

potential project sites

B.

targeted LEED credits

C.

expected water demand

D.

expected energy demand

The results of a building energy model show that a building will consume 2,200,435 kilowatt-hours (kWh) per year (building is served solely by electricity). The building owner wants to achieve Energy and Atmosphere Credit, Green Power and Carbon Offsets. What is the minimum amount of green energy required to be purchased on an annual basis?

A.

770,152 kWh

B.

2,200,435 kWh

C.

550,109 kWh

D.

1,100,218 kWh

For a whole building energy simulation approach, what should be identical for the base building and the proposed building?

Which of the following project types is required to consider the perimeter floor area instead of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight calculations?

A.

Retail

B.

Schools

C.

Healthcare

D.

Core and Shell

Which of the following will contribute to reducing the heat island effect?

A.

Artificial turf grass

B.

Intensive vegetated roof

C.

Steep sloped roof with initial SRI of 35

D.

Low sloped roof with initial Solar Reflectance Index (SRI) of 64

Which of the following is required to earn Energy and Atmosphere Credit, Renewable Energy Production if using a Solar Photovoltaic System?

A.

Carbon offsets

B.

Daylighting strategies

C.

Passive solar strategies

D.

Produced electricity consumed on-site

Smoking is prohibited inside LEED-certified buildings in order to eliminate the health risks associated with environmental tobacco smoke. Which building type is exempt from this requirement?

A.

Office projects

B.

Healthcare projects

C.

Warehouse projects

D.

Residential projects

The project team achieved a strategy not addressed in the LEED Green Building Rating System, which proved to be a significant, measurable environmental benefit for the project. What can the project team do in order to get a benefit for this strategy?

A.

Submit a regional priority credit

B.

No benefit can be achieved since the strategy is not included in the rating system

C.

Submit the manufacturer's product declaration

D.

Submit an innovation credit

Minimizing light trespass is a key component of which of the following credits?

A.

Energy and Atmosphere Credit, Optimize Energy Performance

B.

Energy and Atmosphere Prerequisite, Minimum Energy Performance

C.

Sustainable Sites Credit, Light Pollution Reduction

D.

Indoor Environmental Quality Credit, Interior Lighting

A topographic assessment of a project site located 150 ft. (45 m) from a water body was conducted. The results of the slope analysis show that the site is generally sloping 6% to 8% to the northwest over most of the site, with some steep slopes located at the eastern edge of the property, which may impact the runoff volume. Which one of the following LEED credits or prerequisites will be affected by these results?

A.

Sustainable Sites Credit, Rainwater Management

B.

Sustainable Sites Prerequisite, Environmental Site Assessment

C.

Location and Transportation Credit, Sensitive Land Protection

D.

Location and Transportation Credit, High-Priority Site