What ensures that a project transitioning into implementation also smoothly transitions into appropriate Architecture Governance?

A.

Implementation Strategy

B.

Implementation Governance Model

C.

Transition Plan

D.

Migration Plan

Complete the following sentence. In the ADM documents which are under development and have not undergone any formal review and approval process are_______________.

A.

Called ‘’draft’’

B.

Invalid

C.

In between phases

D.

Known as ‘’Version 0.1’’

What is an objective of the ADM Implementation Governance Phase?

A.

To provide continual monitoring of the governance framework

B.

To ensure conformance for the target architecture

C.

To finalize the Implementation and Migration Plan

D.

To establish the resources for architecture governance

Which of the following statements about architecture partitioning are correct?

    It is equivalent to architecture levels.

    It enables different groups of architects to own and develop specific parts of an architecture.

    It is implemented following a generally applicable partitioning model.

    It is used to simplify the management of an Enterprise Architecture.

A.

1 & 4

B.

1 & 3

C.

2 & 3

D.

2 & 4

Which of the following is a responsibility of an Architecture Board?

A.

Determining the scope of an architecture compliance review

B.

Allocating resources for architecture projects

C.

Conducting assessments of the maturity level of architecture discipline within the organization

D.

Achieving consistency between sub-architectures

What is presented as ”striking a balance between positive and negative outcomes resulting from the realization of either opportunities or threats?

A.

Agile development

B.

Architecture Security

C.

Transition Management

D.

Risk Management

Consider the following descriptions of deliverables consumed and produced across the TOGAF ADM cycle.

Which deliverables match these descriptions?

A.

1 Architecture Requirements Specification - 2 Request for Architecture Work - 3 Statement of Architecture Work - 4 Architecture Principles

B.

1 Statement of Architecture Work - 2 Architecture Principles - 3 Architecture Requirements Specification - 4 Request for Architecture Work

C.

1 Architecture Principles - 2 Architecture Requirements Specification - 3 Request for Architecture Work - 4 Statement of Architecture Work

D.

1 Request for Architecture Work - 2 Statement of Architecture Work - 3 Architecture Principles - 4 Architecture Requirements Specification

Which of the following is a purpose of Phase A of the TOGAF ADM?

A.

Identifying key stakeholders

B.

Defining the Enterprise strategy

C.

Describing the target architecture

D.

Developing an Enterprise Architecture Capability

Which ADM Phase includes creation of an Enterprise Architecture Capability?

A.

Phase A

B.

Phase H

C.

Phase G

D.

Preliminary Phase

Consider the following statements:

1. Groups of countries, governments, or governmental organizations (such as militaries) working together to create common or shareable deliverables or infrastructures

2. Partnerships and alliances of businesses working together, such as a consortium or supply chain

What are those examples of according to the TOGAF Standard?

A.

Enterprises

B.

Organizations

C.

Business Units

D.

Architectures Scopes