The environment in which a product will be used changes and emerges continually. What is the

effect on the Product Backlog?

(choose the best answer)

A.

The requirements specification document, describing the Product Backlog items,

must be updated to ensure stability.

B.

The Product Backlog evolves to reflect what the product needs to be most valuable.

C.

There is no effect, the Product Backlog must stay the same until the end of the

project.

D.

The Product Backlog is archived and a new Product Backlog is created to take its

place

Which phrase best describes a Product Owner?

(choose the best answer)

A.

Go-between for the Developers and customers.

B.

Requirements engineer.

C.

Team manager.

D.

Value maximizer.

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

(choose the best answer)

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Scrum Team's ability to deliver.

D.

Its Definition of Done.

E.

All of the above.

If burndown charts are used to visualize progress, what do they track?

(choose the best answer)

A.

Work remaining across time.

B.

Accumulated cost.

C.

Accumulated business value delivered to the customer.

D.

Individual worker productivity.

What percent of the time should a Product Owner dedicate to the Scrum Team?

(choose the best two answers)

A.

100%.

B.

Enough time to avoid the waste that is created by delaying answers to the

Developers.

C.

As much as the stakeholders want to budget. Business analysts take over the

role the rest of the time.

D.

40%, or more if the stakeholders agree.

E.

Enough time to ensure that the product Increment is valuable and useful.

F.

Just enough time to keep the Developers from complaining.

As Sprint Planning progresses, the workload is getting to be greater than the Developer's

capacity to meet the Sprint Goal. Which actions make the most sense to take?

(choose the best two answers)

A.

Potentially remove or change selected Product Backlog items.

B.

The Developers ensure that the Product Owner is aware, start the Sprint and

monitor progress.

C.

Cancel the Sprint.

D.

Start the Sprint and recruit additional Developers.

E.

Ask the Developers to work overtime for this Sprint and promise that it will not

happen again.

You work as a Product Owner for a small company and your Scrum Team employee retention

rate has been falling. Data from exit interviews suggests that the Developers are:

. Frustrated by interruptions and low-value meetings.

. Feel that their work is not "meaningful."

You need to address this quickly, since the cost to train new Developers is very high in a small

organization like yours.

To increase the likelihood of improving the retention rate, what additional measurements should

you consider when determining improvements?

(choose the best answer)

A.

The Innovation Rate, which is the ratio of new work to total work.

B.

The On-Product Index, the ratio of product work to total work.

C.

Employee Net Promoter Scores.

D.

All of the above.

The Definition of Done is used to:

(choose the best three answers)

A.

Increase transparency.

B.

Describe the purpose, objective, and timebox of each Scrum event.

C.

Create a shared understanding of when work is complete.

D.

Describe the work that must be done before the Sprint can be declared

complete.

E.

Inform the Developers on how many Product Backlog items to select in a Sprint.

A separate Product Backlog is needed for every:

(choose the best answer)

A.

Product.

B.

Scrum Team.

C.

Portfolio.

D.

Program.

E.

All of the above.

Organizations should reduce their investment in a product when the product's:

(choose the best answer)

A.

Unrealized Value is very small.

B.

Current Value is very low.

C.

Current Value is very high.

D.

Unrealized Value is very large.

E.

None of the above.