The only person who can abnormally terminate a Sprint is?

(choose the best answer)

A.

The Developers.

B.

The Scrum Master.

C.

The Product Owner.

D.

The Stakeholders.

Complete this sentence: The more uncertain you are about customer needs or market desires

(choose the best two answers)

A.

the smaller each release should be.

B.

the more you should focus on validating customer needs.

C.

the more likely it is that you should invest in a different product.

D.

the more important a risk management plan becomes.

When many Scrum Teams are working on the same product, should all of their Increments be

combined every Sprint?

(choose the best answer)

A.

No, each Scrum Team stands alone.

B.

Yes, otherwise the Product Owner and stakeholders are unable to accurately inspect

the Increment.

C.

Yes, but only for Scrum Teams whose work has dependencies.

D.

No, that is far too hard and must be done in a hardening Sprint.

The most important thing a Product Owner can do is:

(choose the best answer)

A.

Determine the release schedule and contents.

B.

Ensure that all stakeholder needs are met.

C.

Function as the single source of truth for all requirements.

D.

Maximize the value delivered by the product.