Which of the following are Kanban practices for Scrum?

(choose the best answer)

A.

Visualizing flow, limiting WIP, actively managing the Work in Progress (WIP),

inspecting & adapting the Workflow.

B.

Kaizen, remove delays, visualize policies, pull system.

C.

Small batches, limit WIP, eliminate waste, Kaizen.

D.

Class of service, cost of delay, visualize the Workflow, limit WIP, manage flow.

E.

T-shirt size estimation, service level expectations, limit WIP.

Which of the following is NOT an essential component to initially achieving flow?

(choose the best answer)

A.

Ensuring the Product Backlog is refined frequently.

B.

Limiting Work in Progress (WIP).

C.

Visualizing your Workflow.

D.

Actively managing WIP.

E.

Inspecting & adapting your Workflow.

True or False: The Scrum framework already contains elements that create a pull system.

A.

True

B.

False

In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Limits?

A.

When they want to improve their Cycle Time, flow, and focus.

B.

When there is unplanned urgent work that emerges during the Sprint.

C.

When they see that the average story size they are working on is growing.

D.

When they have extra capacity during the Sprint and want to start some new work items from the Sprint Backlog.

True or False: A Scrum Team using Kanban does not need to craft a Sprint Goal during Sprint Planning. They can instead create one “on-demand” as new work flows into the Sprint Backlog.

A.

True

B.

False

True or False: Little's Law is used to forecast a Scrum Team's output.

A.

True

B.

False

What are the four key flow metrics in Scrum with Kanban?

(choose the best answer)

A.

Work in Progress (WIP), Velocity, Lead Time, Cycle Time.

B.

Throughput, Work in Progress (WIP), Velocity, Lead Time.

C.

Velocity, Lead Time, Cycle Time, Cost.

D.

Work in Progress (WIP), Work Item Age, Throughput, Cycle Time.

True or False: When the Developers add Kanban to Scrum, the way they use the Sprint Goal

during their Daily Scrum changes.

A.

True

B.

False

Which of these statements about Sprints and Kanban is NOT correct?

A.

A Scrum Team will eventually stop using Sprints if they correctly implement Kanban.

B.

The Sprint is an example of an explicit policy for how a team is working.

C.

The Sprint is an example of limiting Work in Progress (WIP).

D.

The Sprint is an example of a cadence.

A service level expectation (SLE) consists of which two items?

(choose the best two answers)

A.

A cost of delay.

B.

A probability.

C.

A forecasted date.

D.

A period of elapsed days.