What should the Scrum Master do if the Developers complain that the Daily Scrum is just a "status update" meeting?

A.

Explain that the intent of the Daily Scrum is to inspect progress towards the Sprint Goal

B.

Cancel the Daily Scrum and have status update meetings instead

C.

Reduce the occurrence for this meeting to once a week

D.

Make Daily Scrum an optional meeting for the Developers to attend

Taylor, a Scrum Master, was asked for their advice on how large a Scrum Team should be. Which of these responses is correct?

A.

"The typical size of an effective Scrum Team is ten or fewer."

B.

"Size doesn't matter as long as the Scrum Master coordinates the work in collaboration with the Product Owner."

C.

"Bigger teams communicate better, are more productive and produce better results."

D.

"When a team expands beyond ten, activities, like verification and operations, are assigned to a different team."

If Scrum Teams become too large, they should

A.

Split into sub-teams based on function

B.

Reorganize into multiple cohesive Scrum Teams and share the same Product Goal and Product Backlog

C.

Divide into separate teams each with their own Product Owner

D.

Do nothing and focus on delivering a usable product Increment

A Developer had an issue with no hardware to test the software. The Scrum Master contacted the hardware manager to help resolve the issue. What characteristic is the Scrum Master exhibiting?

A.

Disciplinarian

B.

Project Manager

C.

Authoritarian

D.

Leadership

The Sprint Backlog belongs solely to the

A.

Scrum Master.

B.

Developers.

C.

Product Owner.

D.

Scrum Team.

Which of the following is an activity of Product Backlog management?

A.

Clearly expressing Product Backlog items

B.

Creating Sprint tasks

C.

Facilitating the Daily Scrum

D.

Planning the Sprint Backlog

A lightweight framework that helps people, teams and organizations generate value through adaptive solutions for complex problems is known as

A.

Kanban.

B.

Scrum.

C.

Agile.

D.

Waterfall.

Which of the following is a Scrum Artifact?

A.

Definition of Done

B.

Sprint Backlog

C.

Sprint Goal

D.

Sprint Burndown Chart

When the goal, scope and product domain are not understood by the Scrum Team, the Scrum Master should

A.

Direct the Developers to stop working until the Product Owner improves the acceptance criteria.

B.

Cancel the Sprint and schedule a new Planning meeting.

C.

Do nothing because this is the responsibility of the Product Owner.

D.

Facilitate a discussion between the Stakeholders, Product Owner and Developers.

In which event are impediments to the Sprint Goal shared?

A.

Daily Scrum

B.

Sprint Planning

C.

Sprint Retrospective

D.

Sprint Review