During Program Increment (PI) Planning, a scrum of scrums occurs just before the draft plan review. The Scrum Master from one team raises an issue that one of the Product Managers just showed up to the planning area with a priority wish list of items. These items do not align with the Feature prioritization. What is the most likely planning anti-pattern causing this sudden impediment?

A.

There is strong alignment between business and marketing

B.

Planning decisions have been centralized

C.

Prioritization by Product Management was performed autonomously not collaboratively

D.

There is no social network that Solution development relies on

What is one action to support a Continuous Integration (CI) culture?

A.

Make integration results visible

B.

Purchase a CI tool

C.

Secure senior leadership support before starting CI

D.

Follow up with CI ceremonies

(Which statement is a value from the Agile Manifesto?)

A.

Individuals and interactions over processes and tools

B.

Customer collaboration over following a plan

C.

Apply systems thinking

D.

Customer collaboration over a constant indefinite pace

Becoming a coach requires a shift from old behaviors to new ones. What are three ex-amples of new coaching behaviors? (Choose three.)

A.

Facilitate team problem-solving

B.

Focus on business value delivery

C.

Drive toward specific outcomes

D.

Fix problems for the team

E.

Ask the team for the answer

F.

Focus on deadlines

When does the Plan-Do-Check-Adjust cycle occur in scrum?

A.

As part of the lteration retrospective

B.

In the daily stand-up

C.

At the lteration review

D.

A cross all scrum events

Which statement is true about SAFe Iteration Goals?

A.

They describe the value of planned Features and Enablers

B.

They provide key performance indicators (KPIs) for tracking progress and value realization

C.

They enable teams to keep aligned with PI Objectives

D.

They provide quantifiable metrics to be used in retrospectives

What is the best way to foster flow of value, innovation, and apply Lean budgeting in the Enterprise?

A.

Determine Epic job size using the Lean business case

B.

Launch Agile Release Trains

C.

Implement the Lean Portfolio Management core competency

D.

Coordinate all Agile Release Trains to provide feedback for cost of delay factors

The Agile Release Train (ART) is near the end of the final Iteration of their first Program Increment. Integration into staging is more challenging than estimated. They add a week to the Innovation and Planning (IP) Iteration for integration and testing. Why is this a bad idea?

A.

Overall train velocity goes up and the time-to-market goes down

B.

It substantially decreases the predictability of the Solution Intent

C.

It reduces the overall predictability established through cadence and synchroniza-tion

D.

It decreases job satisfaction by removing autonomy and purpose

What is the Release Train Engineer's (RTE's) role during the final plan review during PI Planning?

A.

Verify that each team's uncommitted objectives have lower business value than the committed PI Objectives to reflect proper prioritization

B.

Encourage discussion of each team's product Vision as part of the final plan review

C.

Facilitate all teams when they are presenting their final plans to the entire ART

D.

Manage the ROAMing of each team's risks

What is the Scrum Master's role in team breakout #1?

A.

Create mitigation plans for each risk

B.

Resolve dependencies with other teams

C.

Raise team level risks

D.

Facilitate the coordination with other teams for dependencies