How does a Release Train Engineer view the role of functional managers on the Agile Release Train?

A.

As decision makers

B.

As developers of people

C.

As a content authority for work

D.

As problem solvers

Communicating the Vision to the Agile Release Train during Program Increment Planning supports which SAFe Core Value?

A.

Transparency

B.

Program Execution

C.

Alignment

In the SAFe work item hierarchy, Features are decomposed into what?

A.

Stories

B.

Sub-Tasks

C.

Tasks

D.

Capabilities

Product Management is responsible for which activity?

A.

Establishing an architectural vision for the Agile Release Release Train

B.

Defining Program Backlog content

C.

Prioritizing the Portfolio Backlog

In addition to Innovation and Planning, what else does the IP Iteration provide time for?

A.

An estimating guard band

B.

An opportunity to integrate and perform end-to-end testing

C.

Building in quality and compliance

D.

Additional planned work

What is the only true objective measure of an Agile Release Train?

A.

System Demo

B.

Scrum of scrums

C.

Cumulative flow diagram

D.

Team status report

What practice can help to identify bottlenecks in the flow of work?

A.

Visualizing the flow of all work and track progress of individual items

B.

Comparing transaction costs, holding costs and business value realization

C.

Measuring lead time for all work in progress

D.

Modeling overall process flow during value stream identification

What is one recommended practice when planning across large time zone differences?

A.

Allow for overlapping hours

B.

Choose the time zone with the most team members

C.

Choose one time zone for planning, then rotate for the next PI

D.

Plan by time zone, then consolidate the plans

What is one benefit of the Innovation and Planning (IP) Iteration?

A.

It allows for additional planned work

B.

It allows for building in quality and compliance

C.

It provides an estimating guard band

D.

It provides an opportunity to integrate and perform end-to-end testing

The goal of Lean is to deliver the maximum customer value in the shortest sustainable lead time while providing what else?

A.

The highest possible quality

B.

A Continuous Delivery Pipeline

C.

Significant team contributions

D.

Improved capacity allocation