The ART is near the end of the final Iteration of its first PI. Integration into staging is more challenging

than estimated. The ART adds a week to the Innovation and Planning (IP) Iteration for integration and

testing. Why is this action considered an anti-pattern?

A.

Overall, train velocity goes up, and the time-to-market goes down

B.

It decreases job satisfaction by removing autonomy and purpose

C.

It reduces the overall predictability established through cadence and synchronization

D.

It substantially decreases the predictability of the Solution Intent

Which two actions can the Release Train Engineer take to facilitate team growth? (Choose two.)

A.

Provide a team vision

B.

Encourage continuous learning

C.

Encourage skill specialization

D.

Ensure time is allocated for innovation and planning

E.

Facilitate conflict

What is a strategy a Product Owner can use during Program Increment Planning to mini-mize dependencies?

A.

Change the definition of done

B.

Move Stories on their team's backlog to another team

C.

Reprioritize Epics

When looking at a program board at the end of program increment (Pl) planning, what does it mean when a feature is placed in a team's swim lane with no strings?

A.

That the feature can be completed by that team independently

B.

That the team has not broken the feature into stories yet and has not identified dependencies

C.

That it has dependencies on teams in other Agile release trains (ARTs) or Solution Trains

D.

That the team has been assigned, but the feature’ uépendencies have not been identified yet

What is this statement describing? "Agile Teams continuously adapt to new circumstanc-es and enhance the methods of value delivery."

A.

Continuous Improvement

B.

Continuous Delivery

C.

Continuous Integration

D.

Continuous Deployment

What are three actions to take to support a Continuous Integration (CI) culture? (Choose three.)

A.

Purchase a CI tool

B.

Ensure fixing a failed integration attempt is always the top priority

C.

Secure senior leadership support before starting CI

D.

Integrate often

E.

Follow up with CI ceremonies

F.

Make integration results visible

Which two actions can be taken immediately during the management review and prob-lem-solving meeting? (Choose two.)

A.

Change the business priorities

B.

Recognize the team with the highest velocity

C.

Combine teams to increase velocity

D.

Change the scope

E.

Hire new people

At which two stages will the Agile Release Train (ART) act as a one-team culture? (Choose two.)

A.

Performing - Creating a flow of knowledge across the teams and the ART

B.

Norming - Teams begin to form communities

C.

Storming - Fostering continuous improvement

D.

Collaborating - Pairing and sharing across the ART

E.

Forming - The leaders will start to emerge

Program Increment (PI) Objectives should be written in the SMART format. What does the "R" in SMART stand for?

A.

Realistic

B.

Required

C.

Random

D.

Rationalized

What is the Release Train Engineer's (RTE's) role during the final plan review during PI Planning?

A.

Verify that each team's uncommitted objectives have lower business value than the committed PI Objectives to reflect proper prioritization

B.

Encourage discussion of each team's product Vision as part of the final plan review

C.

Facilitate all teams when they are presenting their final plans to the entire ART

D.

Manage the ROAMing of each team's risks