Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
The various work packages in the project are described as individual______________. Choose the correct answer.
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
Which object is relevant in assembly processing to create an assembly order for the SD document?
What could be a reason to use expert mode in the valuation method for results analysis?
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question