Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.

What benefit do they have when using delivery from project (CNSO).

A.

With delivery from projects You can generate goods issues for project without creating delivery documents.

B.

With delivery from projects good receipt are automatically posted while saving.

C.

With delivery from projects you can generate purchase requisitions for sub-contractors.

D.

With the delivery from project you can deliver material component assigned to your network.

A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

A.

The network activity is assigned to a WBS element

B.

The network is assigned to a sales order item

C.

The material master of the component must permit project stock management

D.

The Project Stock indicator is set in the project definition (non-valuated or valuated)

E.

A procurement indicator must be assigned to the activity

Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question

A.

Saving a supplier invoice

B.

Saving a service entry shee

C.

Saving a goods receipt

D.

Saving a purchase order

You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question

A.

If the maximum reduction level is less than 100

B.

If the reduction strategy is set in the network header

C.

If the reduction strategy is set in each activity

D.

If the appropriate reduction type is set in the parameters for network scheduling

The various work packages in the project are described as individual______________. Choose the correct answer.

A.

WBS elements

B.

Project definitions

C.

Tasks

D.

Activities

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

A.

The network profile

B.

The control key

C.

The table of MRP controllers

D.

The scheduling parameters for the network

Which object is relevant in assembly processing to create an assembly order for the SD document?

A.

Project profile

B.

Item category

C.

Requirement class

D.

Control key

What could be a reason to use expert mode in the valuation method for results analysis?

A.

Billing WBS elements belonging to different company codes

B.

Assignments of different accounts for postings to financial accounting

C.

Usage of different line ID

D.

Valuation in different currencies

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

A.

Set up the requirement date aligned with the activity finish date and an offset of 15 days.

B.

Set up the requirement date manually as February 5.

C.

Set up the requirement date aligned with the activity start date and an offset of 5 days

D.

Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question

A.

Goods receipt into unvaluated project stock

B.

Recording of external services in the service entry sheet

C.

Goods receipt of a non-stock item

D.

Goods receipt into valuated project stock