Cost & Budget.

A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?

A.

Settlement rules

B.

Costing Sheet

C.

Investment profile.

D.

Results analysis key

Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.

A.

Usage of cost elements is mandatory

B.

Sales prices are maintained in the DIP profile

C.

DIP is used to create a quotation

D.

Sources can be based on line items

E.

Material determination is mandatory

Float time is calculated during scheduling.

Which of the following statements about float time are correct?

Note: There are 3 correct answers to this question

A.

Float time can be negative

B.

Activities with the time constraint "Must start on" always have a negative float time

C.

The float time of WBS elements is calculated by extrapolation

D.

By default, critical activities have a float time, which is less than or equal to zero

E.

The maximum size of a free float is as large as the total float of an activity

In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

A.

Scheduling and capacity category

B.

Scheduling and distribution key

C.

Control key of an activity

D.

Capacity planner group in the network header

How can you search in the structure overview based on the user status? Note: There are 2 correct answers to this question

A.

By searching for the status profile

B.

By searching via status selection profile

C.

By searching via status combination code

D.

By searching for the individual status

Cost & budget

A service Company use project management and they complain that the system does not prevent their project manager from

exceeding their budget.

What action do you have tsolve the problem?

A.

Activate availability control For projects in the control area. Enter the plan data for each WBS element.

B.

Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.

C.

Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.

D.

management in the project definition. Enter the budget in the master data of the top WBS element.

E.

Activate commitment

Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question

A.

Basic dates

B.

Forecast dates

C.

Baseline dates

D.

Planned dates

Resources

Which of the following transactions can you use to post actual cost for external processing.

Note : there are 2 correct answer for this question.

A.

Approval of a service entry sheet

B.

Posting a goods receipt

C.

Creating a service entry sheet

D.

Approval of a good receipt.

E.

Creating a purchase order.

Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

A.

An activated Scheduling indicator in the control key of the internal processing activity

B.

Whether the work for the internal activity is greater than its duration

C.

The unit (for example, hour, day) of the field Normal Duration field of the activity

D.

The relationships between activity elements

E.

The factory calendar in the work center used for the internal processing activity

The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element

A.

Calculation of actual values

B.

Goods receipt for purchase order

C.

Creation of purchase orders

D.

Activity allocation